121 US 255 Cleveland Rolling-Mill Co v. Rhodes

121 U.S. 255

7 S.Ct. 882

30 L.Ed. 920

CLEVELAND ROLLING-MILL CO.
v.
RHODES and another, Ex'x, etc.1

April 11, 1887.

In Error to the Circuit Court of the United States for the Northern District of Illinois.

This was an action brought by Rhodes and Bradley, conpartners, and citizens of Chicago, in the state of Illinois, against the Cleveland Rolling-mill Company, a corporation of the state of Ohio, upon the following agreement in writing, signed by both parties:

'This agreement, made this sixteenth day of February, A. D. 1880, by and between Rhodes & Bradley, of Chicago, Ills., and the Cleveland Rolling-mill Co., of Cleveland, Ohio, witnesseth that said Rhodes & Bradley have sold to the said Cleveland Rolling-mill Co. the entire product of fourteen thousand (14,000) tons iron ore, to be manufactured into pig-iron, with charcoal, by the Leland Furnace Co., of Leland, Mich., said furnace to make as nearly all numbers one and two iron as possible, and to be shipped in vessel cargoes as repidly as possible to the Cleveland Rolling-mill Co., at Cleveland, Ohio, during the season of navigation of 1880. Such portion of the product of said ores as is made after the close of navigation of 1880 is to be shipped by vessel to Cleveland on the opening of navigation of 1881, or as near the opening as possible; said Cleveland Rolling-mill Co. to have the privilege of ordering the iron, which may be made too late for shipment by lake during the season of 1880, through by rail to Cleveland during the winter of 1880 and 1881, they to pay the additional expense of hauling to railroad, and freighting through to Cleveland by rail, over and above what it would cost Rhodes & Bradley to ship by lake on the opening of navigation 1881. Said Cleveland Rolling-mill Co. agree to receive said iron as rapidly as shipped, and to pay forty-five dollars ($45) per ton (2,240 lbs.) cash for same delivered on rail or vessel at Cleveland, Ohio. The Cleveland Rolling-mill Co. are to have the option of taking a portion of the iron delivered at Chicago, Ills., at the same price and on the same terms and conditions as stated above for delivery in Cleveland; said Cleveland Rolling-mill Co. to furnish a good and suitable dock at which to unload vessels, either at Cleveland or Chicago, and to pay vessels any demurrage which they may be justly entitled to by reason of delay in furnishing a dock at which they can be discharged. The iron ore o be furnished at the Leland Iron Co., out of which said iron is to be manufactured, is as follows: 6,000 tons Cleveland mine; 5,000 tons Norway mine; 1,500 tons Rolling-mill mine; 1,500 tons Stephenson mone. And whereas, Rhodes & Bradley's contracts with said mining companies are to the effect that, in case of accidents or strikes at said mines, resulting in reduced output of ore, said companies are to have the provilege of reducing the amounts due Rhodes & Bradley, as above stated, in same proportion as other sales, the said Cleveland Rolling-mill Co. agree not to hold Rhodes & Bradley responsibile for delivery of pig-iron beyond the product of such ores as the mining companies deliver them; also, in case of accidents or strikes at said Leland furnace, resulting in the stoppage of said furnace, then Rhodes & Bradley are not to be held responsible for delivery of pig-iron under the contract, beyond the responsibility of the Leland Iron Co. to them under the contract between said Leland Iron Co. and Rhodes & Bradley, dated January 14, 1880, which contract, as well as Rhodes & Bradley's contracts with the mining companies, is hereby made a part of this agreement.'

Prior to January 14, 1880, the plaintiffs had made agreements in writing with the owners of the four mines for the purchase of the amounts of ore above mentioned, to be delivered by them to the plaintiffs during the season of navigation in 1880. And on January 14, 1880, the plaintiffs made an agreement in writing with the Leland Iron Company, which was the owner and manager of a furnace at Leland, in the state of Michigan, by which the plaintiffs agreed to sell to that company the same amounts of those ores, respectively, 'to be furnished, 1,500 tons in May, 1880, navigation permitting, and 2,500 tons each month thereafter, as nearly as may be, and all to be delivered to vessel before November 1, 1880, and in suitable quantities of each for the mixtures desired by said Rhodes & Bradley;' and also agreed 'to purchase the entire product of pig-iron of the Leland furnace made from the ores so furnished, at the rate of $40 per ton cash, delivered over the rail at Chicago, or $40.25 cash, at Cleveland, at the option of said Rhodes & Bradley, they to provide proper docking facilities for prompt unloading of vessels;' and the Leland Iron Company agreed 'to manufacture pig-iron from said ores as nearly as practicable of the grades which said Rhodes & Bradley shall desire, and to ship same in cargo lots as rapidly as possible after manufacture, during season of navigation, to said Rhodes & Bradley, to Chicago or Cleveland as aforesaid.'

A jury was duly waived by stipulation in writing, and the case was tried by the court, which found specially that all the above contracts were executed and delivered by the parties thereto, and further specially found as follows:

'(3) That the plaintiffs, between May 16 and October 18, 1880, delivered to the Leland Iron Company, at Leland, Michigan, 14,168 tons of iron ore, of which 5,980 tons were from the Cleveland mine, 4,405 tons were from the Norway mine, 1,478 tons were for the Rolling-mill mine, and 2,305 tons were from the Stephenson mine.

'(4) That the ores from the Stephenson mine and the ores from the Norway mine were alike in value and quality, and that Stephenson mine ore was equally as good and identical in quality and value with the ore from the Norway mine.

a'(5) That the Leland Iron Company proceeded, soon after such ores began to arrive at Leland, with proper diligence to manufacture said ores into pigiron, and ship the same in cargo lots, as rapidly as possible after manufacture, from Leland to Cleveland, Ohio, and there delivered the same to the defendant, and the defendant accepted and paid for the same; that before the close of navigation for the season of 1880 the Leland Iron Company had so manufactured and delivered to the defendant 3,421 tons of said pig-iron; that the defendant made no objection to the acceptance of said pig-iron on said contract between the plaintiffs and the defendant, on the ground of the quality of said iron, or of undue delay in the execution of said contract.

'(6) That the navigation between Leland and Cleveland and Chicago closed in the fall of 1880 about November 15th; that the last cargo of iron was shipped from Leland on November 8th, and, although the Leland Iron Company had enough iron manufactured to have furnished another cargo of 502 tons by November 15th, no vessel could be obtained by which to ship it that fall; that, after the close of navigation, the Leland Iron Company continued the manufacture of said ore into pig-iron without unreasonable delay,—and that after November 8, 1880, and up to and including February 28, 1881, the Leland Ireon Company had made 2,100 tons of pig-iron from said ore, and by May 7, 1881, had manufactured, and on hand ready for shipment, about 3,506 tons; that on May 7, 1881, the Leland Iron Company resumed the shipment of said iron in cargo lots to the defendant at Cleveland, and continued such manufacture and shipment in cargo lots as rapidly as possible, so that the entire product of said ore was manufactured and shipped from Leland by and including July 2, 1881, all which cargoes arrived at Cleveland in due course, and were there tendered to the defendant, and the defendant refused to accept said pig-iron, or any part thereof, and refused to pay for the same; that if the average daily product of said furnace from November 8, 1880, to May 8, 1881, had been the same as the average daily product from May 18 to November 8, 1880, all said 14,000 tons of ore would have been made into pig-iron by about May 10, 1881; but, in fact, the furnace was shut down for a time, and part of the time the blast was checked for want of a sufficient supply of charcoal, so that about 1,100 tons of said pig-iron were made after May 8, 1881.

'(7) That in the latter part of the month of February, and again about March 3, 1881, the defendant notified the plaintiffs that it would not accept, under said contract of February 16, 1880, any iron which was made from said ore after December 31, 1880; and that some time during the month of May, 1881, the defendant notified the plaintiffs that it would not accept any more iron from the plaintiffs under said contract.

'(8) That the fair market price of said pig-iron in the cities of Cleveland and Chicago, during the months of March, April, May, June and July, 1881, was $27 per ton; that the total amount of iron manufactured from said 14,000 tons of iron [ore,] and shipped by the Leland Company to the defendant after the opening of navigation in the spring of 1881, was 4,579 tons; and that the difference between the market value of $27 per ton and the contract price was $18 per ton, making a total difference on 4,579 tons of $82,422.'

The court rendered judgment upon the special findings for the plaintiffs in the sum of $82,422, and costs. 17 Fed. Rep. 426. The defendant excepted to the admission of evidence at the trial, to the refusal of the court to make certain special findings requested, and to the judgment for the plaintiffs; and afterwards sued out this writ of error.

Wm. E. Cushing and Geo. F. Edmunds, for plaintiff in error.

J. M. Flower and Enoch Totten, for appellees.

Mr. Justice GRAY, after stating the case as above reported, delivered the opinion of the court.


Advertisement
view counter
1

The original defendant duly pleaded, and has earnestly argued, that the plaintiffs did not perform their contract, in respect either to the nature of the thing furnished, or to its quantity, or to the time of delivery. The principal objections, each of which would require consideration if the decision of the case depended upon it, are as follows: As to the nature of the thing: That the amounts of ore from each of the four mines named, delivered at the furnance and there manufactured into pig-iron, differed from the amounts contracted for, the ores from three of the mines being respectively 20 tons, 595 tons, and 22 tons less, and the ore from the fourth mine 805 tons more. As to the quantity: That the plaintiffs tendered to the defendant the product of 14,168 tons of ore, when the contract was for the product of 14,000 tons only. As to the time of performance: That the pig-iron was not made and shipped 'as rapidly as possible;' and especially that so much of it as had not been made and shipped before the close of navigation, in 1880, was not shipped 'on the opening of navigation of 1881, or as near the opening as possible.'

2

We have not found it necessary to consider the objections as to the kind of iron, or how far any such objections were waived by the defendant, or the effect of tendering too much, or yet the objections to the competency of evidence admitted at the trial, or the variance suggested between the declaration and the proof, because we are of opinion that the delay which took place in the making and shipment of so much of the pig-iron as had not been made and shipped before the close of navigation in 1880 is fatal to the plaintiffs' right to maintain this action. In a case decided upon much consideration at the last term, the general rule was stated as follows: 'In the contracts of merchants, time is of the essence. The time of shipment is the usual and convenient means of fixing the probable time of arrival, with a view of providing funds to pay for the goods, or of fulfilling contracts with third persons. A statement descriptive of the subject-matter, or of some material incident, such as the time or place of shipment, is ordinarily to be regarded as a warranty, in the sense in which that term is used in insurance and maritime law; that is to say, a condition precedent, upon the failure or non-performance of which the party aggrieved may repudiate the whole contract.' Norrington v. Wright, 115 U. S. 188, 203, 6 Sup. Ct. Rep. 12. See, also, Filley v. Pope, 115 U. S. 213, 6 Sup. Ct. Rep. 19; Pope v. Porter, 102 N. Y. 366, 7 N. E. Rep. 304; Rommel v. Wingate, 103 Mass. 327.

3

When a merchant agrees to sell, and to ship to the rolling-mill of the buyer, a certain number of tons of pig-iron at a certain time, both the amount of iron and the time of shipment are essential terms of the agreement. The seller does not perform his agreement by shipping part of that amount at the time appointed, and the rest from time to time afterwards; and the buyer is not bound to accept any part of the iron so shipped.

4

In the case at bar, the plaintiffs were merchants at Chicago, and the defendant was the owner of a rolling-mill at Cleveland. By the agreement between them, made in February, 1880, the plaintiffs sell to the defendant 'the entire product of fourteen thousand tons iron ore, to be manufactured into pig-iron with charcoal,' at a certain furnace, 'and to be shiped in vessel cargoes as rapidly as possible' to the defendant at Cleveland, 'during the season of navigation of 1880,' and 'such portion of the product of said ores, as is made after the close of navigation of 1880, is to be shipped by vessel to Cleveland on the opening of navigation of 1881, or as near the opening as possible.' The plaintiffs thus agree that all of the pig-iron contracted for, that is not made and shipped before the close of navigation in 1880, shall be shipped as early in 1881 as navigation shall be open, and vessels can be obtained. This implies that the whole of the ore shall be made into pig-iron, and ready for shipment as soon as navigation opens, in 1881. The implication is confirmed by the further stipulation that the defendant shall have the privilege, upon paying the additional expense of transportation by land, 'of ordering the iron, which may be made too late for shipment by lake during the season of 1880, through by rail to Cleveland, during the winter of 1880 and 1881.' In short, all the pig-iron not shipped before the close of navigation in 1880 is to be made before the opening of navigation in 1881, and to be then shipped as soon as vessels can be obtained, n less the defendant elects to have it previously forwarded by land.

5

The facts, as found by the court, bearing upon the question of the plaintiffs' performance of their agreement in this particular, are as follows: The whole amount of pig-iron made from the 14,000 tons of ore was 8,000 tons. Of these, 3,421 tons were shipped in 1880, and accepted and paid for by the defendant. At the opening of navigation, early in May, 1881, there were manufactured and on hand, ready for shipment, only 3,506 tons. The remaining 1,073 tons were made afterwards, and the last cargo was not shipped until nearly two months after navigation opened. The general statements in the sixth finding, that the owner of the furnace, after the close of navigation in 1880, 'continued the manufacture of said ore into pig-iron without unreasonable delay,' and on the opening of navigation, in 1881, resumed the shipment of iron to the defendant, 'and continued such manufacture and shipment in cargo lots as rapidly as possible,' are limited and controlled by the more precise statements in the same finding that, if the average daily product of the furnace had been the same from the close of navigation in 1880 to the opening of navigation in 1881, as it had been during the season of 1880, 'all said 14,000 tons of ore would have been made into pig-iron by about May 10, 1881; but in fact the furnace was shut down for a time, and part of the time the blast was checked, for want of a sufficient supply of charcoal, so that about 1,100 tons of said pig-iron were made after May 8, 1881.'

6

The failure to have on hand a sufficient amount of charcoal to keep the furnace at work is not shown to have been due to 'accidents or strikes,' which were contingencies contemplated by all parties, and provided for in the contract sued on. But it was a state of things of which the plaintiffs assumed the risk by undertaking that the whole of the ore should be made into pig-iron ready to be shipped as soon as possible after the opening of navigation in 1881. After the contract for 8,000 tons of pig-iron had been partly performed on both sides, in 1880, by the plaintiffs' having delivered, and the defendant's having accepted and paid for, 3,421 tons of iron, then the thing which, by the terms of so much of the contract as was yet unperformed, the plaintiffs agreed to deliver, and the defendant agreed to take and pay for, was 4,579 tons of pig-iron, made and ready for shipment upon the opening of navigation in 1881, and then shipped as rapidly as possible; and the rights and duties of the parties as to the performance of this part of the contract were the same as if it had been the whole contract between them.

7

The true construction of the contract being that that amount of iron shall be ready to be shipped, and be actually shipped, as soon as navigation permits, 'that is part of the description of the subject-matter of what is sold;' and 'the plaintiff, who sues upon that contract, has not launched his case until he has shown that he has tendered the thing which has been contracted for, and, if he is unable to show that, he cannot claim any damages for the nonfulfillment of the contract.' Lord CAIRNS, in Bowes v. Shand, 2 App. Cas. 455, 468; Norrington v. Wright, 115 U. S. 188, 209, 6 Sup. Ct. Rep. 12. The necessary conclusion is that the defendant was justified in refusing to accept any of the iron shipped in 1881; and whether the notice, previously given by the defendant to the plaintiff, that it would not accept under the contract any iron made after December 31, 1880, might have been treated by the plaintiffs as a renunciation and a breach of the contract, need not be considered, because the plaintiffs did not act upon it as such. Dingley v. Oler, 117 U. S. 490, 503, 6 Sup. Ct. Rep. 850.


Advertisement
view counter
8

It conclusively appearing, upon the facts found by the court below, that the original plaintiffs cannot maintain their action, it is ordered, in accordance with the precedents of Fort Scott v Hickman, 112 U. S. 150, 5 Sup. Ct. Rep. 56, and Allen v. St. Louis Bank, 120 U. S. 20, 7 Sup. Ct. Rep. 460, that the judgment be reversed, and the case remanded to the circuit court, with directions to enter judgment for the original defendant.

1

17 Fed. Rep. 426.