Public-domain · open source
OpenJurist

11 N.C. App. 369

181 S.E.2d 201

Askew's, Inc. v. Cherry

Court of Appeals of North Carolina · decided 1971-05-26

Key passage — most relied on by later courts

“If a party moving for summary judgment presents, by affidavits or otherwise, materials which would require a directed verdict in his favor, if presented at trial, then he is entitled to summary judgment unless the opposing party either shows that affidavits are then unavailable to him, or he comes forward with some materials, by affidavits or otherwise, that show there is a triable issue of material fact.”

quoted by 1 later decision, including 54 N.C. App. 328 - Cox v. Haworth

Relies on 9 N.C. App. 635 - Pridgen v. Hughes

Good law ✅— No negative treatment on recordhow we know

Decided 1971-05-26

How this case has been cited

Cited by 8 later decisions — most recently December 2016

8 state decisions

4019711980199020002010decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

View the full empirical analysis of this case →

GRAHAM, Judge.

¶1 If a party moving for summary judgment presents, by affidavits or otherwise, materials which would require a directed verdict in his favor, if presented at trial, then he is entitled to summary judgment unless the opposing party either shows that affidavits are then unavailable to him, or he comes forward with some materials, by affidavit or otherwise, that show there is a triable issue of material fact. Pridgen v. Hughes, 9 N.C. *373 App. 635, 177 S.E. 2d 425; 6 Moore’s Federal Practice 2d, § 56.11(3), p. 2171.

¶2 The answer and affidavit introduced by Red Carpet show that it has complied with the settlement agreement wherein it was released of all claims arising out of "the' motel project by Cherry and Building. The only attempted showing to the contrary by appellants was the affidavit in which Cherry contended that the settlement agreement required Red Carpet to pay all debts incurred by Building in connection with the motel project.

¶3 Where:the language of a contract is plain and unambiguous the construction is a matter of law for the courts. 2 Strong, N. C. Index 2d, Contracts, § 12, p. 311.

¶4 The settlement agreement in question is clear and unambiguous. Under the agreement, Building was to be paid an amount equal to its audited cost on the project, plus 5% thereof,1 and less amounts already paid under the construction contract' In agreeing that payment was to be made by issuing and delivering checks payable to Building and its creditors, the parties were simply .undertaking to protect Building’s creditors to the extent of the money owed Building by Red Carpet. The method of payment had nothing to do with the amount owed.

¶5 We find no promise in the agreement that the amount owed by Red Carpet to Building, when determined by an audit, would equal the amount of Building’s obligation to its creditors. Building and Cherry have come forward with nothing to show that the audit was inaccurate. Furthermore, they do not deny that they have received payments which the audit reflected were owed them under the agreement. We therefore find, as did the trial judge, that there is no genuine issue as to any material fact in this case.

¶6 Affirmed.

Judges Campbell and Britt concur.