Public-domain · open source
OpenJurist
← 15 Cal. App. 1 - Hettinger v. Thiele

15 Cal. App. 1 - Hettinger v. Thiele’s Empirical Analysis

1910

Citation profile

6
cited by 6 later decisions
2
states following
July 1953
most recently cited

6 state decisions

How this case has been cited

Cited by 6 later decisions — most recently July 1953

6 state decisions

3019101920193019401950decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

Most-quoted passages

The sentences later courts lift from this opinion, ranked by how many decisions quote each — the parts of the opinion doing the work. These counts are smaller than the citation total above because most of the 6 citing decisions cite the case generally; a passage count includes only decisions quoting that exact language verbatim.

  1. ““It was intended that as the work was performed by the contractor he should be entitled to seventy-five per cent of the value of the work so performed, measured by the contract price, that is, for example, when the contractor had placed materials and labor in the building in accordance with the plans and specifications of the value of $1,000, he should be entitled to a payment of $750, and so on from time to time. As the work progressed, and as fast as it progressed and from day to day, the contractor was entitled to seventy-five per cent of its value. Of course it would have been unreasonable for the contractor to have claimed and demanded the amount due from day to day, and insisted upon the architect giving him a certificate from day to day as to the amount that had become due. It must be presumed that the parties intended the contract to be reasonably construed, and that with such view the contractor would only require payment to be made at reasonable intervals as the work progressed, so as to enable him to pay for his materials, and to meet the wages of carpenters and artisans employed by him. In fact this must have been the course pursued, because no question appears to have been made as to the payment of installments up to the time of the earthquake, which payments amounted to $8,800. The twelfth clause of the contract makes provision for loss in case the building should be wholly destroyed by earthquake. . . . The provision as to the loss shows that in case the buildi”
    1 later decision quote this exact passage

How this case has been treated — in progress

Whether each later court followed, distinguished, criticized, or overruled this decision. The treatment classification (task #35) runs highest-cited cases first and lights up here as it reaches this one.