Public-domain · open source
OpenJurist

158 Conn. 611

Logan v. Lenhart

Supreme Court of Connecticut

Decided May 6, 1969

Supreme Court of Connecticut · decided 1969-05-06

Key passage — most relied on by later courts

“Whether the plaintiff authorized the defendants to furnish extra work, whether the plaintiff fully paid for the extras, and whether the defendant . . . rendered any services for CT Page 13390 which he was entitled to recover compensation were purely issues of fact for the referee to resolve. It was his function to weigh the evidence and to determine the facts.”

quoted by 1 later decision, including 1998 Conn. Super. Ct. 13387 - Sigel v. Della Bella, No. Cv 97-0142423s (Nov. 20, 1998)

Relies on Tartaro v. La Conte

Good law ✅— No negative treatment on recordhow we know

Decided 1969-05-06

How this case has been cited

Cited by 8 later decisions — most recently November 1998

8 state decisions

401969197019801990decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

View the full empirical analysis of this case →

Per Curiam.

¶1The amended report of the referee, which is not subject to correction, reveals these facts: The defendant Erna R. Lenhart was the owner of a tract of land with a house thereon located in the town of Southbury. On October 28, 1960, the plaintiff and the defendant Erna R. Lenhart executed a written agreement in which the defendant Erna R. Lenhart agreed to sell the property to the plaintiff for the sum of $47,500. In the agreement, the defendants promised to build an addition to the

¶2*612living room of the house at a cost not exceeding $5000. Soon after the defendants started to construct the addition in accordance with the plans specified in the agreement, the plaintiff desired to make some changes in the original plans. Accordingly, the parties orally agreed upon a number of changes and extras. The defendant Erna R. Len-hart conveyed the property to the plaintiff on January 13, 1961. The total amount of the obligation incurred by the plaintiff to the defendants for the property and improvements thereto was $63,761.63. The plaintiff paid the defendants the sum of $60,218.73, and the balance due the defendants is $3542.90.

¶3None of the plaintiff’s objections to the acceptance of the report has merit. Whether the plaintiff authorized the defendants to furnish extra work, whether the plaintiff fully paid for the extras, and whether the defendant Edison S. Lenhart rendered any services for which he was entitled to recover compensation were purely issues of fact for the referee to resolve. It was his function to weigh the evidence and. to determine the facts. As the trier, the referee was the sole arbiter of the credibility of witnesses and was privileged to adopt whatever testimony he reasonably believed to be credible. Tartaro v. La Conte, 157 Conn. 583, 584, 254 A.2d 912.

¶4There is nothing in this appeal which discredits the findings or the conclusions of the referee. Therefore the trial court did not commit error by accepting the amended report and by rendering judgment thereon.

¶5There is no error.