<p>Appeal, No. 134, Oct. T., 1900, by defendant, from order of C. P. Delaware Co., Dec. T., 1899, No. 240, making absolute a rule for judgment for want of a sufficient affidavit of defense in case of Letitia W. Twining et al., trading as S. B. Twining and Company, Limited, v. E. H. Roberts.</p> <p>Rule for judgment for want of a sufficient affidavit of defense.</p> <p>The contract upon which suit was brought was as follows:</p> <p>“ This instrument of June, 1899, of which E. H. Roberts, of the city of Chester, Pa., herein designed for convenience as the party of the first part, and S. B. Twining & Co., Limited, of Stockton, N. J., herein designed for convenience as the party of the second part.</p> <p>“ Witnesseth, that for and in consideration of the price and payment to he made by the party of the first part, hereinafter mentioned, the party of the second part agrees to furnish without delay all stone necessary to complete the bridge abutments and wing walls of Ninth street bridge, Chester, Pa., in conformity with the plans and specifications. All stone to be subject to the inspection of the City Engineer.</p> <p>“ The party of the second part agrees to furnish said stone on or before day of , 1899, under penalty of dollars per day for each and every day stone remains undelivered after the above mentioned time, unless otherwise agreed. The party of the first part agrees to unload all boats within ten (10) working hours after their arrival. At the expiration of the ten (10) hours he agrees to pay demurrage at the rate of five dollars ($5.00) per day for use of boat. The party of the first part agrees to pay for the stone on the 15th of every month for stone set during the preceding month as the work progresses. For the face stone the sum of seven dollars and forty cents ($7.40) per cubic yard, for coping ten dollars and forty cents per- cubic yard, and for backing two dollars and twenty-five cents ($2.25) per cubic yard. One third of the wall where face stone and backing are used together is to be paid for as facing, and the remaining two thirds to be paid for as backing; where backing is used only, then it is to be measured and paid for as backing.</p> <p>“ In witness whereof, we have hereunto affixed our hands this 23d day of June, A. D. 1899.</p> <p>(Signed) “ E. H. Roberts.</p> <p>“ S. B. Twining & Co.”</p> <p>Defendant’s supplemental affidavit of defense was as follows:</p> <p>Edward H. Roberts, the above named defendant, being duly sworn according to law, says by way of supplement to his affidavit of defense heretofore filed in the above stated case, that under the said contract, a copy of which is set forth in the statement of plaintiffs’ claim, filed, the said plaintiff was required to furnish the stone without delay. In addition to the said requirement of the said contract, the treasurer and manager of the plaintiffs’ company, Charles T. Eastburn, at the time of the making of the said contract, undertook for and on behalf of the said plaintiff to furnish the said stone and make full delivery thereof by July 1, 1899. The plaintiff company did not furnish the said stone without delay, and did not complete the delivery thereof by July 1,1899, but on July 1,1899, a large part of the stone, to wit: one fourth, remained undelivered. The said stone remaining undelivered on July 1,1899, was fuh ther delayed by the plaintiff in the delivery thereof until December 1,1899. By reason of the said delay and the said breach of contract on the part of the said plaintiff, the said defendant has been subjected to great damage and expense, and particularly has incurred a liability to the King Bridge Company of $750 under the following circumstances: The said defendant, relying upon the said undertaking of the said plaintiff, as to the time of the delivery of the said stone, entered into a contract with the King Bridge Company to construct the abutments of the said bridge, and undertook to have the same completed on the first day of July, 1899. By reason of the said failure on the part of the said plaintiff to perform its said contract as aforesaid,- the said defendant was unable to perform his said contract with the King Bridge Company, and complete said abutments at the time specified, whereby the defendant was subjected to damages to the said King Bridge Company, to the amount of the said sum of $750, being at the rate of thirty days at $25.00 per day.</p> <p>The court entered judgment for want of a sufficient affidavit of defense in an opinion by Johnson, P. J.</p> <p>Error assigned was the order of the court.</p>