172 Mo. App. 186

Mullins v. Everett

Missouri Court of Appeals

Decided May 19, 1913

Missouri Court of Appeals · decided 1913-05-19

<p>1. SEWER: Ordinance: Specifications. Wliere an ordinance for the construction of a sewer which hy the city charter is required to specify the dimensions, material and character of the work, sets out on its face such dimensions, material and the character of the work, together with all necessary specifications, then it is unnecessary that a duplicate of such specifications be referred to as on file with the city engineer.</p> <p>2. -: -: -: -: -. A city charter required ordinances for the construction of sewers to ordain the dimensions, material and character of the sewer. An ordinance was passed naming the dimensions and material and referring to the specifications prepared for the construction of the sewer. But, in fact, the specifications were not in existence when the ordinance was passed and were not made out and approved by the board of public works until ten days afterwards. They contained many substantial requirements not set out in the ordinance. And it was held that the proceedings were void and tax bills issued for the work were invalid.</p>

Relies on Galbreath v. Newton · Barber Asphalt Paving Co. v. O'Brien · Dickey v. Porter

Good law ✅— No negative treatment on recordhow we know

Ajbttrmed · Decided 1913-05-19

How this case has been cited

Cited by 5 later decisions — most recently January 1951

5 state decisions

2019131920193019401950decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

View the full empirical analysis of this case →

ELLISON, P. J.

¶1Plaintiff’s action is based on tax bills for the building of a district sewer in Kansas City, Missouri. The trial was by the court without the aid of a jury and judgment was rendered for defendant.

¶2The charter of the city (Sec. 10, Art. 9, Charter 1898) provides that the city may, with the approval of the board of public works, construct district sewers, which “shall be of such dimensions, material and character as shall be prescribed by ordinance.” On the 2d of November, 1903, the city passed an ordinance for the construction of the sewer in question. Section 3 of this ordinance reads that: “Said sewer shall conform in detail to plans and specifications prepared for the construction of said sewers, said plans now on file in the office of the board of public works, marked approved and dated October 29, 1903.” These specifications were not made out or approved by the board of public works until ten days (November 12th) after the passage of the ordinance. What were called “plans” for the sewer were approved and on file with the board of public works four days before the ordinance was passed as is recited in the section just quoted.

¶3The ground claimed to invalidate the tax bill is that at the time the ordinance was passed the specifications were not in existence and therefore could not have been a part of the ordinance, and in .consequence the ordinance did not comply with the charter requir*189ing it to specify the dimensions, material and character of the sewer. This requirement of the charter is a mandatory legislative function which cannot be delegated by the city council.

¶4The ordinance need not embody the specifications in the face of the ordinance itself, but may refer to them as being at a certain place. They then become a part of the ordinance itself. [Galbreath v. Newton, 30 Mo. App. 380, 392.]

¶5• But manifestly the specifications must have been considered by the city council and be in existence when the ordinance is passed, else, necessarily, they could not be a part of it. The claim that they could be, has been characterized as a gross absurdity. [Dickey v. Holmes, 109 Mo. App. 721; McCormick v. Moore, 134 Mo. App. 669; Paving Co. v. O’Brien, 128 Mo. App. 267.]

¶6In avoidance of this plain requisite, plaintiff says that the face of the ordinance itself covers the requirement of the charter. In other words, that it contains the specifications for the sewer and that therefore separate specifications were not necessary and their not ■being in existence when the ordinance was passed was of no consequence. The circuit court took that view and gave a declaration that if the evidence showed such to be the fact, the finding would be for the plaintiff. But the court found it was not a fact. We are of the opinion that the court’s view, as expressed in the declaration given, was correct; for, if the specifications for the work are embodied in the ordinance itself, it would render unnecessary their repetition in a separate paper.

¶7It is therefore only necessary to ascertain if there was evidence to justify the conclusion of the court, and we find it abundant. In addition to what is stated and required in the ordinance, the specifications provide for the excavations, trenches, the manner of their construction; the brick and rubble masonry; the kind and *190character of mortar, concrete, cement and other material; syphon traps are provided for and their character prescribed; the character of the work and the places where certain material is to be nsed on portions of the work required by the ordinance proper; foundations for the sewer at different places and the manner of their construction. These are but a part of the specifications. They cover near fifteen pages of printed matter, making it impracticable to set them out. It is sufficient to say of them that they include many important and vital requirements to a lawful performance of the work, which are not found in the face of the ordinance. We think it- a complete answer to plaintiff’s suggestion that the ordinance itself contained all the specifications necessary, to call attention to the fact that confining the ordinance to the provisions embodied in its face, specifications could be- drawn, without conflicting therewith, which would reduce the character, grade or quality of the work and much of the material, as well as the value of the sewer completed, in a very substantial degree. The record shows that, practically speaking, the ordinance, unaided by the specifications set out, would have afforded little protection to the property holder.

¶8We are at a loss to understand why plaintiff should cite us to Dickey v. Porter, 203 Mo. 1, 35, 36. The specifications for the sewer work in that instance were prepared and placed on file with the board of public works before the passage of the ordinance and the ordinance referred to and adopted them. That case is strongly against the situation in which the facts place plaintiff in this case. Nor do we see that Fox v. Schoenemann, 52 Mo. 348, has any bearing on the present record.

¶9Plaintiff however takes the position that the specifications were in existence and on file when the ordinance was passed. This claim'is founded on evidence that there were printed blanks, or what may be termed *191blank specifications, printed and kept on band in tbe city engineer’s office by order of tbe city council. These were provided for use whenever needed and have been likened by ns in a former case to blank deeds which notaries, and frequently county recorders, kept on hand. [Richardson v. Walsh, 142 Mo. App. 328; McCormick v. Moore, 134 Mo. App. 669.]

¶10We have examined other authorities cited by plaintiff, but find them not applicable to the facts of the present case.

¶11After full consideration of the record, we conclude we have no ground for interference with the judgment, and it is accordingly affirmed.

All concur.