← 175 F.2d 698 - Power Service Corp. v. Joslin

Power Service Corp. v. Joslin’s Empirical Analysis

175 F.2d 698 · 1949

Citation profile

16
cited by 16 later decisions
4
states following
March 2010
most recently cited

5 federal appellate · 1 district · 5 state decisions

How this case has been cited

Cited by 16 later decisions — most recently March 2010

5 federal appellate · 1 district · 5 state decisions

6019491950196019701980199020002010decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

Relationships

Relies on Continental Casualty Co. v. Schaefer · Girard Life Insurance Annuity Trust Co v. Cooper · Priest v. Oehler · Lingenfelder v. Wainwright Brewing Co. · Alaska Packers' Ass'n v. Domenico

Most-quoted passages

The sentences later courts lift from this opinion, ranked by how many decisions quote each — the parts of the opinion doing the work. These counts are smaller than the citation total above because most of the 16 citing decisions cite the case generally; a passage count includes only decisions quoting that exact language verbatim.

  1. “As for the Contracting Officer, although his signature . . . was not appended to the formal contract until September 11, 1944, yet the record shows that he was fully informed of all that transpired, and received copies of most of the correspondence that took place . . . . The clause requiring his written approval was one inserted solely for the protection of the government, which clearly had the right to, and did waive it. Under these circumstances, the Corporation is hardly in a position to claim that this provision, which all parties ignored, operated to postpone its obligation under its bid. Id. at 702 [footnote omitted].”
    1 later decision quote this exact passage · from the majority
  2. “[t]he subcontract shall be subject to the written approval of the Architect-Engineer-Manager [the general contractor] and the Contracting Officer, and shall not be binding until so approved”
    1 later decision quote this exact passage · from the majority

How this case has been treated — in progress

Whether each later court followed, distinguished, criticized, or overruled this decision. The treatment classification (task #35) runs highest-cited cases first and lights up here as it reaches this one.