Bennett v. United States’s Empirical Analysis

1967

Citation profile

46
cited by 46 later decisions
1
states following
November 2013
most recently cited

5 federal appellate · 1 district · 1 state decisions

How this case has been cited

Cited by 46 later decisions — most recently November 2013 · most notably Max Drill, Inc. v. United States (1970), Sun Shipbuilding & Dry Dock Co. v. United States (1968)

5 federal appellate · 1 district · 1 state decisions

150196719701980199020002010decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

Relationships

Applies 41 U.S.C. § 321

Relies on United States v. Utah Construction & Mining Co. · United States v. Carlo Bianchi & Co. · United States v. Anthony Grace & Sons, Inc. · Griffin v. California · J. D. Hedin Construction Co. v. United States

Most-quoted passages

The sentences later courts lift from this opinion, ranked by how many decisions quote each — the parts of the opinion doing the work. These counts are smaller than the citation total above because most of the 46 citing decisions cite the case generally; a passage count includes only decisions quoting that exact language verbatim.

  1. “Changes. The Contracting Officer may at any time, by written order, and without notice to the sureties, make changes in the work within the general scope of the contract, including changes in the drawings and specifications. If such changes cause an increase or decrease in the amount of work under this contract or in the time necessary for its performance, an equitable adjustment will be made in the price or the time allowed for performance, or both, and the contract shall be modified in writing accordingly. All claims by the Contractor for adjustment under this paragraph must be asserted within 30 days from the date the change is ordered, and in the meantime, the Contractor shall proceed with the work as so changed. [Emphasis added.]”
    1 later decision quote this exact passage · from the majority

How this case has been treated — in progress

Whether each later court followed, distinguished, criticized, or overruled this decision. The treatment classification (task #35) runs highest-cited cases first and lights up here as it reaches this one.