Tins was an action on special contract, averring: the declaration alleges that Snider was to quarry seven hundred yards of stone, and deliver the same to McClelland as fast as quarried, which McClelland was to remove, paying therefor one dollar and ten cents per yard, to be measured in the wall of certain buildings which McClelland was to erect for the Illinois Central Eailroad Company.

Good law ✅— No negative treatment on recordhow we know

Decided 1856-11-15

How this case has been cited

Cited by 3 later decisions — most recently September 1895

3 state decisions

1018561860187018801890decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

View the full empirical analysis of this case →

Caton, J.

¶1The first and second instructions, which the court gave for the plaintiff below, were wrong. The first excepted to, is as follows: “If the jury believe, from the evidence, that there was a special contract between the parties in relation to quarrying stone, although the same might not have been performed by either party, yet if plaintiff quarried and delivered stone to defendant, and defendant accepted and appropriated the same to his own use, the plaintiff is entitled to recover the reasonable value of the stone, deducting therefrom any damages sustained by defendant by failure of plaintiff to deliver the same according to contract, and any payment made on the same.” This instruction was wrong, because it allowed the plaintiff to recover the reasonable val/ae of the stone, irrespective of the contract price; whereas, the rule of law is, that the contract price shall govern the measure of compensation, wherever it can he made to apply, whether that he more or less than the reasonable value of the stone. This identical question, in almost precisely such a case, was decided at the last term of this court, in this division, and demands no further discussion here. Had that case been reported at the time of the trial of this cause, no doubt the instruction would have been different. See Brigham v. Hawley, 17 Ill. R. 38.

¶2The next instruction excepted to is this : “ If the contract was to measure said stone in the walls of the dépót building in Centraba, and defendant appropriated said stone to other-purposes, as wells and culverts, not stipulated for in said contract, it was a breach of said contract, and releases the plaintiff from his liability on the same.” This instruction was clearly wrong. It was a matter of no moment what became of the stone, so far as the plaintiff was concerned, if he had the proper facilities for measuring them. The only object of the provision, that they should be measured in the walls of the dépót, was to provide a rule by which they should be measured, not that the stone should have a particular spot for a resting-place. The object of the provision was as well attained by placing the stone in one wall as another, so that it was accessible.

¶3The judgment must be reversed and the cause remanded.

¶4Judgment reversed.