Public-domain · open source
OpenJurist

2016 DNH 62

Unity School District v. Vaughn, et al.

New Hampshire District Court

Decided March 23, 2016

New Hampshire District Court · decided 2016-03-23

Applies 28 U.S.C. § 1332 (Class Action Fairness Act of 2005)

Applies NH 507 § 507:7

Relies on Bell Atlantic Corp. v. Twombly · Ashcroft v. Iqbal · Securities & Exchange Commission v. Tambone

Decided 2016-03-23

                     UNITED STATES DISTRICT COURT

                      DISTRICT OF NEW HAMPSHIRE


Unity School District,
     Plaintiff

     v.                                   Case No. 15-cv-155-SM
                                          Opinion No. 
2016 DNH 062
Vaughn Associates, Inc.,
and Scott Vaughn,
     Defendants

     v.

School Administrative Unit #6,
Excel Mechanical, Inc.,
Superior Walls of Hudson Valley, Inc.,
and Town of Unity,
     Third-Party Defendants


                              O R D E R


     This case arises from two contracts between the Unity School

District and Vaughn Associates, Inc., pursuant to which Vaughn

Associates agreed to design and, subsequently, oversee

construction of a new elementary school in Unity, New Hampshire.

Those contracts were terminated in early 2014, and this

litigation ensued.    Initially, the Unity School District filed a

four-count writ in state court against Vaughn Associates and its

principal, Scott Vaughn (collectively, “Vaughn”).   Vaughn then

removed the action to this court, on grounds that the parties are

diverse.   Subsequently, it filed a ten-count third-party

complaint against several entities, none of which was a party to

its contracts with the Unity School District.
     Two of those third-party defendants - the Town of Unity and

School Administrative Unit #6 - now move to dismiss all claims

advanced against them, asserting that none states a viable cause

of action.   See generally Fed. R. Civ. P. 12(b)(6).   Vaughn

objects.    For the reasons discussed, those motions are granted.



                         Standard of Review

     When ruling on a motion to dismiss under Rule 12(b)(6), the

court must “accept as true all well-pleaded facts set out in the

complaint and indulge all reasonable inferences in favor of the

pleader.”    SEC v. Tambone, 
597 F.3d 436, 441
 (1st Cir. 2010).

Although the complaint need only contain “a short and plain

statement of the claim showing that the pleader is entitled to

relief,” Fed. R. Civ. P. 8(a)(2), it must allege each of the

essential elements of a viable cause of action and “contain

sufficient factual matter, accepted as true, to state a claim to

relief that is plausible on its face,” Ashcroft v. Iqbal, 
556 U.S. 662, 678
 (2009) (citation and internal punctuation omitted).



     In other words, “a plaintiff’s obligation to provide the

‘grounds’ of his ‘entitlement to relief’ requires more than

labels and conclusions, and a formulaic recitation of the

elements of a cause of action will not do.”   Bell Atl. Corp. v.

Twombly, 
550 U.S. 544, 555
 (2007).    Instead, the facts alleged in


                                  2
the complaint must, if credited as true, be sufficient to “nudge”

plaintiff’s claims “across the line from conceivable to

plausible.”   
Id. at 570
.   If, however, the “factual allegations

in the complaint are too meager, vague, or conclusory to remove

the possibility of relief from the realm of mere conjecture, the

complaint is open to dismissal.”       Tambone, 
597 F.3d at 442
.



                             Background

     Accepting the allegations of the third-party complaint as

true - as the court must at this juncture - the relevant facts

are as follows.   In 2009, the New Hampshire Department of

Education voted to close the Town of Unity’s elementary school

because it failed to comply with state building, fire safety, and

educational requirements.   In 2010, Scott Vaughn volunteered to

donate his design services to assist the Unity School District in

preparing a proposal to construct a new elementary school and to

secure voter approval of a bond to fund the project.



     In August of 2010, that bond was approved by the voters of

the school district.   Subsequently, the Unity School District

entered into an Architectural Services Contract with Vaughn

Associates, under which Vaughn Associates agreed to design the

new elementary school.   Shortly thereafter, the Unity School

District entered into a second contract with Vaughn Associates,


                                   3
pursuant to which Vaughn Associates would act as the project’s

construction manager.   Once the project got underway, however, it

was plagued by difficulties and delays.   Eventually, in January

of 2014, Vaughn Associates resigned as construction manager and,

approximately two months later, it sent notice to the Unity

School District terminating the Architectural Services Agreement.

In terminating that contract, Vaughn Associates cited

“impracticability, frustration of purpose, lack of good faith and

fair dealing, and non-payment.”   Third-Party Complaint (document

no. 8) at para. 125.



     In March of 2015, the Unity School District filed suit in

state court against Vaughn Associates, Inc. and Scott Vaughn,

advancing claims of negligence, breach of contract, negligent

misrepresentation, and violations of New Hampshire’s Consumer

Protection Act.   Vaughn removed the action, invoking this court’s

diversity subject matter jurisdiction.    See generally 
28 U.S.C. § 1332
.   And, as noted above, Vaughn subsequently filed a ten-

count third-party complaint against School Administrative Unit #6

(“SAU #6”), Excel Mechanical, Inc., Superior Walls of the Hudson

Valley, and the Town of Unity, New Hampshire.



     Pending before the court are motions filed by SAU #6 and the

Town of Unity, seeking dismissal of all claims asserted against


                                  4
them.    Counsel for the parties presented their arguments in legal

memoranda, as well as at a hearing before the court on December

1, 2015.



                              Discussion

        Before addressing the specifics of the pending motions to

dismiss, it probably bears noting that, with the exception of its

claim against the Town of Unity for intentional interference with

contractual relations, Vaughn does not seek to recover damages

for actual losses or injuries it sustained.    Instead, Vaughn

seeks contribution or, better still, complete indemnification

from both the Town and SAU #6 for harms sustained by the Unity

School District and any damages Vaughn may, in the future, owe to

the Unity School District.    See, e.g., Third-Party Complaint at

paras. 138, 144, 205, and 212.    Vaughn has clearly, repeatedly,

and unambiguously proclaimed that it is (with the one exception

noted above) pursuing claims for contribution and implied

indemnification.    Accordingly, its claims must be treated as such

(despite allegations in the third-party complaint that might

suggest Vaughn is pursuing the third-party defendants for harm it

suffered as a consequence of their allegedly tortious conduct).




                                   5
I.   Claims Against SAU #6.

     Vaughn advances two claims against SAU #6: one for statutory

contribution, pursuant to N.H. Rev. Stat. Ann. (“RSA”) 507:7-f

(count one); and one for common law indemnity (count two).

Third-Party Complaint at paras. 138 and 144.    See also Vaughn’s

Memorandum in Opposition (document no. 30-1) at 2-3 (“[Vaughn’s]

Third-Party Complaint against SAU seeks contribution and/or

indemnity for the actions of SAU which caused or contributed to

the Project issues and delays.”).   The New Hampshire Supreme

Court has explained the distinction between contribution and

indemnification as follows:


     [I]ndemnity is distinguished from contribution because
     whereas indemnity shifts the entire burden of loss from
     one tortfeasor who has been compelled to pay it, to
     another whose act of negligence is the primary cause of
     the injured party’s harm, contribution is partial
     payment made by each or any of jointly or severally
     liable tortfeasors who share a common liability to an
     injured party.


Gray v. Leisure Life Indus., 
165 N.H. 324, 330
 (2013) (citations

and internal punctuation omitted) (emphasis supplied).



     A.   Count One - Statutory Contribution.

     In count one of its third-party complaint, Vaughn asserts

that SAU #6: (a) negligently prepared “financial, programming,

educational specification and preliminary design data” upon which

Vaughn relied in formulating its cost and budgetary estimates,

                                6

id.
 at para. 131; (b) negligently failed to provide Vaughn with a

geotechnical report in a timely manner, which forced Vaughn to

revise its budget estimates; and (c) employed a “poor and

untimely payment process,” 
id.
 at para. 137 - all of which

“cause[d] delays or otherwise constitue[d] an impediment to the

project.”   
Id.
 at para. 143.   Accordingly, says Vaughn:


     To the extent [Vaughn] is liable to [Unity School
     District] for negligence or for any other tort-based
     recovery (which [Vaughn] denies in all respects), SAU
     #6 is responsible to [Vaughn] for the amount of its
     proportionate liability pursuant to RSA 507:7-f.


Id.
 at para. 138 (emphasis supplied).1



     There are, however, fundamental problems with that claim.

First, the third-party complaint does not allege that SAU #6 owed

and breached any cognizable common law duties that proximately

caused the injuries for which Unity School District seeks

compensation.   In other words, Vaughn has failed to allege

sufficient facts to suggest that SAU #6 is a joint tortfeasor

that should be held to account for its proportionate share of

Vaughn’s liability to the School District.   Instead, Vaughn

alleges that it has suffered some vague, potentially contingent,


     1
          RSA 507:7-f provides that, subject to certain specific
conditions, “a right of contribution exists between or among 2 or
more persons who are jointly and severally liable upon the same
indivisible claim, or otherwise liable for the same injury, death
or harm.”

                                  7
harm as a consequence of having relied upon inaccurate

information allegedly provided by SAU #6 and because SAU #6

allegedly employed “a poor and untimely payment process.”    Simply

stated, Vaughn’s claims do not give rise to a viable cause of

action for statutory contribution; even charitably construed, the

third-party complaint fails to state a viable basis for finding

SAU #6 was a joint tortfeasor (i.e., breached a recognized common

law duty) that proximately caused the damages for which Unity

School District seeks compensation from Vaughn.   See Leisure Life

Indus., 
165 N.H. at 330
 (“contribution is partial payment made by

each or any of jointly or severally liable tortfeasors who share

a common liability to an injured party.”) (emphasis supplied).

See also Restatement (Third) Torts: Apportionment Liab. § 23 (Am.

Law. Inst. 2000) (noting that the party seeking contribution must

demonstrate that the party from whom it seeks contribution

proximately caused the plaintiff’s injuries).



     Moreover, even if Vaughn had alleged the elements of a

viable contribution claim under New Hampshire statutory law, this

action is not the proper vehicle by which to pursue that claim.

The court has previously discussed this issue in detail, see

Connors v. Suburban Propane Co., 
916 F. Supp. 73
 (D.N.H. 1996),

and that analysis need not be repeated.   It is sufficient to note

that the court concluded:


                                8
        Because its use to implead third-party contribution
        defendants would violate the Rules Enabling Act (by
        limiting plaintiffs’ and enlarging defendant’s
        substantive rights under applicable state law), Fed. R.
        Civ. P. 14 cannot be invoked, without plaintiffs’
        consent, to bring a contribution action premised on
        
N.H. Rev. Stat. Ann. § 507:7
-f & g against a third-party defendant in this diversity action.


Id. at 81
.    Because the plaintiff in this action - Unity School

District - has not consented to Vaughn’s efforts to pursue a

statutory contribution claim against SAU #6 as a third-party

defendant, that claim (even if properly pled) cannot be advanced

here.    See RSA 507:7-g IV(c) (“If and only if the plaintiff in

the principal action agrees, a defendant seeking contribution may

bring an action in contribution prior to the resolution of the

plaintiff’s principal action, and such action shall be

consolidated for all purposes with the principal action.”).



        B.   Count Two - Common Law Indemnity.

        New Hampshire common law recognizes three distinct types of

indemnity: derivative or imputed by law, express, and implied.

See Leisure Life Indus., 
165 N.H. at 327
.        Here, Vaughn is

pursuing an implied indemnity claim.    See Vaughn Opposition

Memorandum at 12.    The problem Vaughn faces, however, is that

“under New Hampshire law, a right to indemnification is rarely

implied.”    Johnson v. Capital Offset Co., No. 11-CV-459-JD, 
2013 WL 5406619
, at *8, 
2013 DNH 127
 (D.N.H. Sept. 25, 2013) (citation

                                   9
omitted).    According to the New Hampshire Supreme Court, “This

disinclination [to infer an indemnification obligation] reflects

a simple notion founded in pragmatism and fairness, that those

who are negligent should bear responsibility for their

negligence.”   Dunn v. CLD Paving, Inc., 
140 N.H. 120, 123
 (1995)

(citation and internal punctuation omitted).



     Nevertheless, the Supreme Court of New Hampshire has

recognized that, under limited circumstances, one party may have

an implied obligation to indemnify another.     So, for example, the

court has held that it might be appropriate to find an implied

indemnification obligation when one party sells a product that

contains a defectively-designed or defectively-manufactured

component.   If the plaintiff’s injuries arise solely from that

defective component, and if the seller’s only negligence was in

failing to discover that defect, the seller might have a viable

claim against the product’s manufacturer for implied

indemnification.   See Jaswell Drill Corp. v. General Motors

Corp., 
129 N.H. 341, 346
 (1987).      Alternatively, the court has

recognized that:


     [A]n implied agreement to indemnify may exist when an
     indemnitor performs a service under contract
     negligently and, as a result, causes harm to a third
     party in breach of a nondelegable duty of the
     indemnitee.



                                 10
Leisure Life Indus., 
165 N.H. at 328
.     Plainly, however, the

facts of this case are distinguishable from those in both Jaswell

and Leisure Life.   SAU #6 (the indemnitor) had no contract with

Vaughn, nor did it supply Vaughn with a defective product for use

in the design or construction of the new school.    Moreover, the

third-party complaint fails to allege how SAU #6’s allegedly

wrongful conduct harmed Unity School District (the third party)

in breach of a duty owed by Vaughn (the indemnitee).



     According to the third-party complaint, SAU #6 should be

required to indemnify Vaughn for any liability Vaughn may have to

the Unity School District because:


     SAU #6 knew or should have known that [Vaughn] would
     rely on its budgetary data as it constructed the new
     Unity elementary school;

     SAU #6 knew or should have known that its data was
     flawed;

     SAU #6 took no steps to ensure its data was accurate or
     to correct its data in a timely manner; and

     SAU #6 knew or should have known that its failure to
     timely process payment requests and/or reimbursement
     requests would cause delays or otherwise constitute an
     impediment to the project.


Third-Party Complaint at paras. 140-43.    But, the third-party

complaint does not link any of that allegedly wrongful conduct to

harm suffered by Unity School District.    In other words, the

third-party complaint fails to allege sufficient facts to warrant

                                11
the conclusion that SAU #6’s “negligence [was] the primary cause

of the injured party’s harm,” Leisure Life Indus., 
165 N.H. at 330
, and, therefore, that SAU #6 should be required to indemnify

Vaughn.    The allegedly inaccurate “budgetary data” provided by

SAU #6 was relied upon by voters in approving the $4.7 million

bond and the supplemental $550,000 bond.   See Third-Party

Complaint at paras. 28, 37, and 90.   And, according to Vaughn,

SAU #6’s alleged failure to process payment requests in a timely

manner harmed Vaughn (which says it stepped in to make those

payments), not the School District.   See 
Id.
 at paras. 91-95.



      While the Third-Party Complaint is confusing, this much is

plain: it fails to allege facts sufficient to support the rarely-

recognized common law claim for implied indemnification against

SAU #6.



II.   Claims Against the Town of Unity.

      A.    Count 11 (Contribution) and Count 12 (Indemnification).

      Largely for the reasons set forth above, Vaughn’s third-

party claims against the Town of Unity fail to state viable

causes of action for either statutory contribution or implied

indemnification.




                                 12
     B.      Count 10 - Intentional Interference with Contract.

     To set forth the essential elements of a viable claim for

intentional interference with contractual relations, the third-

party complaint must plausibly allege that: (1) Vaughn had an

economic relationship with Unity School District; (2) the Town of

Unity was aware of that relationship; (3) the Town of Unity

intentionally and improperly interfered with that relationship;

and (4) Vaughn was damaged by such interference.      Hughes v. N.H.

Div. of Aeronautics, 
152 N.H. 30, 40-41
 (2005).      The Town of

Unity asserts that the third-party complaint fails to adequately

allege both the third and fourth elements.



      With regard to the third element, “[o]nly improper

interference is deemed tortious in New Hampshire.”      Roberts v.

General Motors Corp., 
138 N.H. 532, 540
 (1994) (emphasis in

original).    And, in determining whether an actor’s conduct was

“improper,” the New Hampshire Supreme Court has held that

consideration must be given to several factors, including the

nature of the actor’s conduct, his or her motives, and the

interests advanced by the actor.       See 
Id.,
 at 540-41 (quoting

Restatement (Second) of Torts § 767 (Am. Law. Inst. 1979)).

Finally, of course, Vaughn must allege facts sufficient to permit

the reasonable inference that conduct attributable to the Town




                                  13
proximately caused the damages for which Vaughn seeks

compensation.



     Turning to the facts pled in the third-party complaint,

Vaughn alleges that:


     The Town allowed its employees, elected officials
     and/or agents to use their positions in an abusive
     manner to fight the new Unity Elementary School
     Project.

     The Town knew or should have known that the new Unity
     Elementary School Project was vital to the continued
     success of the Town and yet, through its agents, it
     sought without justification to delay or defeat the
     project.

     As a result of the conduct of the Town, the contractual
     relationship between [Vaughn] and [Unity School
     District] became frayed.

     Ultimately, as a result of the conduct of the Town,
     [Vaughn] had to terminate its contract with [Unity
     School District].

     The actions of the Town, by and through its agents,
     constitute intentional interference with an
     advantageous business relationship.

     As a result of the interference of the Town, [Vaughn]
     has suffered damages, costs and loss of reputation.


Third-Party Complaint at paras. 197-202.   In support of that

claim, Vaughn alleges that employees and agents of the Town

(e.g., the Fire Chief and Building Inspector), as well as a

“strong, vocal ‘anti-tax’ element in the Town,” id. at paras 21,

61, 96, working with the State Fire Marshal, sought to impose


                               14
additional (costly and time-consuming) requirements on the

project.   See, e.g., Id. at para. 66-68 (“For example, the Fire

Chief insisted that the parking lot design incorporate the

ability to park two ladder fire trucks side-by-side directly

adjacent to the school building.     This was in excess of the

access requirements contained in the fire code.    The necessary

upgrade to the parking lot essentially required that it be

designed on par with components of a major highway thereby

significantly increasing the costs of construction.”).    See also

Id. at para. 96 (“In the mean time, members of the anti-tax

element of the Town (inside and outside of the Town government)

continued to contact the [State Fire Marshal] pointing out

alleged deficiencies in the building design and construction.”).



      According to Vaughn, the issues raised by agents of the Town

“were largely, if not completely fabricated and constituted

nothing more than an attempt to use the [State Fire Marshal] as a

tool to stop or delay construction of the school.”    Id. at para.

98.   Yet, Vaughn seems to claim that the Town somehow “forced” it

to comply with those fabricated, unreasonable, and unjust demands

by modifying the design elements of the school and/or its

construction techniques, and thereby proximately caused Vaughn to

suffer damages.




                                15
     What Vaughn has failed to identify (either in its legal

memoranda or at oral argument), and what the third-party

complaint lacks, is some causal connection between the alleged

conduct of the Town’s employees/agents and the harm Vaughn claims

to have suffered.   At oral argument, counsel for Vaughn stated

that when Vaughn received “fabricated,” “unreasonable,” and

“unjust” demands (from individuals not party to its contracts) to

alter the specifications of the architectural drawings,

construction techniques, or building materials, it simply

acquiesced to those demands in an effort to appease opponents of

the project and to maintain a good relationship with its

principal, the Unity School District.    And, in the process, it

incurred substantial additional costs.   That, in turn, caused its

relationship with the Unity School District to become “frayed.”



     But, it is important to remember that Vaughn had two

contracts with the Unity School District: first, an Architectural

Services Contract, by which it agreed to design the proposed

elementary school, Third-Party Complaint at 39; and, second, a

contract pursuant to which Vaughn agreed to act as the project’s

construction manager, id. at para. 43.    As was discussed at

length at oral argument, when faced with opposition from members

of the public and demands from the building inspector, fire

chief, and state fire marshal, for design or construction


                                16
changes, Vaughn perhaps should have presented those matters to

the client for decision.   Vaughn could have turned to its client

- the Unity School District - and explained that it would

certainly make the requested changes, so long as the client

agreed and executed a change order assuming responsibility for

the additional costs and resultant delays.   Instead, Vaughn

apparently acquiesced, and made the changes requested by third

parties, no doubt expecting that those changes could be

implemented within the existing budget and time requirements.

But, to claim that the Town somehow unlawfully “forced” Vaughn to

unilaterally make design and construction changes is not

plausible.   Nor is it plausible to say that the alleged conduct

on the part of the Town’s employees and agents amounted to

unlawful interference with Vaughn’s contractual relationship with

the Unity School District.   It is as if a neighbor demanded that

the School District construct an abnormally high fence around the

school’s playground and, for reasons satisfactory to Vaughn, it

unilaterally agreed to do so.   Then, after the School District

sued Vaughn for cost overruns and delays, Vaughn sued the

neighbor for intentional interference with contractual relations.

Few would think that Vaughn had a viable claim.



     The Town’s citizens, employees, and agents were of course

free to demand that the School District and Vaughn design and


                                17
oversee construction of an elementary school more to their

liking, if they so chose.   But in the face of such demands,

Vaughn had a contractual remedy: seek agreement and appropriate

change orders from the Unity School District, or simply refuse to

meet the demands of interested non-parties to the controlling

contracts.   Having apparently elected a third course of action -

to unilaterally make the requested changes to the final design

and/or construction methods for which the Unity School District

contracted - Vaughn cannot now seek to recover its losses from

the Town on a theory of intentional interference with contractual

relations.



     In short, the third-party complaint lacks plausible

allegations that wrongful conduct of the part of the Town, its

employees, and/or its agents improperly interfered with Vaughn’s

obligation to honor its own contractual relationship with Unity

School District and, thereby, proximately caused harm to Vaughn.

Even assuming, as Vaughn alleged at oral argument, that the

demands made upon it by the Town’s agents were “intentionally

excessive [and made] for the purposes of killing the project,”

see Draft of Oral Argument Transcript at 18, such conduct does

not, under the circumstances presented, give rise to a viable

claim for intentional interference with contractual relations.

Vaughn had the contractual obligation to refuse to make requested


                                18
modifications, or to first obtain the School District’s agreement

and appropriate change orders.    It did neither.   It cannot now

complain that the costs associated with its voluntary assumption

of obligations outside the contracts must be borne by the Town.



                             Conclusion

      For the foregoing reasons, as well as those discussed at

oral argument and in the memoranda submitted by the third-party

defendants, the motions to dismiss filed by the Town of Unity

(document no. 13) and School Administrative Unit #6 (document no.

24) are granted.    Counts 1, 2, 10, 11, and 12 of the Third-Party

Complaint are dismissed.


      SO ORDERED.


                                 ___________________________
                                 Steven J. McAuliffe
                                 United States District Judge

March 23, 2016

cc:   Jerrol A. Crouter, Esq.
      Keriann Roman, Esq.
      Demetrio F. Aspiras, III, Esq.
      Kenneth B. Walton, Esq.
      Michael E. Coghlan, Esq.
      Andrew B. Livernois, Esq.




                                  19

/2016/dnh/62 · .json · Public domain