Public-domain · open source
OpenJurist

207 Mass. 304

Tobin v. Kells

Massachusetts Supreme Judicial Court

Decided January 4, 1911

Massachusetts Supreme Judicial Court · decided 1911-01-04

<p>Practice, Civil, Auditor’s report, Exceptions. Contract, Rescission, Performance and breach, Consideration. Words, “Perfect satisfaction.”</p> <p>No exception lies to the denial of a motion to recommit an auditor’s report with an instruction to the auditor to report all the evidence on which he based a certain finding.</p> <p>In refusing to entertain an exception to the denial of a motion to recommit an auditor’s report, it was said, that, although it is a proper exercise of judicial discretion for a trial judge to recommit an auditor’s report where it appears that the auditor has made an erroneous ruling which is likely to deprive a party of important rights, yet the mere fact that an auditor has erred upon abstract questions of law, which can be raised afterwards at the trial, does not make it necessary to recommit his report.</p> <p>In refusing to entertain an exception to the denial of a motion to recommit an auditor’s report with an instruction to the auditor to report all the evidence on which he made a certain finding, it was said, that, even if this court had had authority to review the exercise of the discretion of the trial judge, the bill of exceptions here presented no means of doing so, as it did not show what facts, if any, were before the judge when he denied the motion.</p> <p>In an action on an account annexed for labor and materials furnished by the plaintiff to the defendant in the remodelling of certain houses, the defendant relied on a contract in writing for the work, which the plaintiff had abandoned, and the plaintiff contended that the abandonment of the contract in writing was by mutual agreement of the parties. An auditor found and reported that the contract in writing had been annulled by the parties. The plaintiff testified that he asked the defendant whether he was going to make a payment to the plaintiff in accordance with an oral agreement modifying the terms of the original contract, that the defendant said “No,” whereupon the plaintiff said that under the circumstances all he could do was to quit, to which the defendant replied, “ Quit and be damned,” and that thereupon the plaintiff did quit and brought his action. Held, that the finding of the auditor was prima facie evidence on which the jury had a right to find that the contract in writing was rescinded, and that they could make the same finding upon the testimony of the plaintiff, as an assent by the defendant to the plaintiff’s proposition to abandon the work would be sufficient although given angrily and with an oath.</p> <p>In an action on an account annexed for labor and materials furnished by the plaintiff to the defendant in the remodelling of certain houses, the defendant contended that the plaintiff could not recover because he had not completed his contract, and the plaintiff contended that he was prevented from doing so by the wrongful conduct of the defendant. The plaintiff testified that, shortly after a contract in writing had been made for the work, he told the defendant that he had been disappointed in regard to obtaining money to use upon the work and that it would be very hard for him to keep on with the contract, and that an oral agreement then was made between the parties changing the terms of the contract in writing as to the payments to be made by the defendant, so that the defendant should pay to the plaintiff a certain sum of money each week, if the payments thus to be made did not exceed the next instalment fixed by the contract in writing, and there was evidence on which the jury could have found, in spite of evidence of the defendant to the contrary, that a modification of the contract was made, and that it was made in consequence of the plaintiff’s statement to the defendant, which was understood by both parties to be in substance a statement that the plaintiff could not go on with his work and must abandon the contract unless it was modified. It appeared that the defendant afterwards' refused to make any further payments required by the modified agreement testified to by the plaintiff, and that the plaintiff thereupon abandoned the work and sued the defendant for damages. Held, that, under the decisions of this court, the modification of the contract, which could have been found to have been made, could have been found to have had a good consideration and to be binding on the parties, and that therefore the jury could find that the defendant unjustifiably prevented the plaintiff from going on with his work under the contract, and thus released him from any obligation to complete it.</p> <p>A contract in writing to do certain work in remodelling certain houses to the “ perfect satisfaction ” of the owner, means that the work shall be performed in such a manner that a reasonable man ought to be satisfied with it.</p>

Relies on Hanson & Parker, Ltd. v. Wittenberg · Handy v. Bliss · Hastings v. Lovejoy

Good law ✅— No negative treatment on recordhow we know

Decided 1911-01-04

How this case has been cited

Cited by 23 later decisions — most recently July 1981

23 state decisions

9019111920193019401950196019701980decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

View the full empirical analysis of this case →

Sheldon, J.

¶11. The defendant’s motion for the recommital of the auditor’s report with the instruction to the auditor to report all the evidence upon which was based the finding that the special contract had been annulled by the parties was addressed solely to the discretion of the presiding judge, and the defendant had no right of exception to the denial of the motion. This has been so often declared that we cite only a few of the later cases. Butterworth v. Western Assurance Co. 132 Mass. 489. Carew v. Stubbs, 161 Mass. 294. Craig v. French, 181 Mass. 282. Tripp v. Macomber, 187 Mass. 109, 110. Allwright v. *310Skillings, 188 Mass. 538. No doubt it would be a proper exercise of judicial discretion to recommit a report if it appeared that the auditor had made an erroneous ruling which would be likely to deprive a party of important rights. But ordinarily the opportunity given to try a case fully before a jury and thus to raise all questions of law, with the fact that the auditor’s findings are not conclusive, will enable both parties to safeguard their rights on all material questions. The mere fact that an auditor may have erred on some abstract questions of law would not make it necessary to recommit his report.

¶2But upon these exceptions, as in Hunneman v. Phelps, 199 Mass. 15, even if we had authority to review the discretion of the judge below, we have not the means of doing so. • We do not know what facts, if any, were shown or agreed to before him; we could not say that his action was wrong upon the face of the report, and nothing else is before us.

¶32. Under the clear and distinct instructions given them, the jury must have found that the written contract between the parties was no longer in force; that either the defendant had prevented the plaintiff from performing that contract and so the latter had a right to treat it as no longer binding (Bailey v. Marden, 193 Mass. 277 ; Posner v. Seder, 184 Mass. 331, 333; Brown v. Woodbury, 183 Mass. 279), or else that it had been annulled by the consent of both parties. But the defendant contends that such a finding was unwarranted upon either ground.

¶4The auditor found and reported that the contract had been annulled by the parties. This furnished prima facie evidence in favor of that contention. Fisher v. Doe, 204 Mass. 34, 39, 40. The jury had a right so to find. And the plaintiff’s testimony indicated that his proposition to abandon the work had been assented to by the defendant. Nickerson v. Weld, 204 Mass. 346, 357. An assent would be sufficient though given angrily and with an oath. This too was for the jury.

¶5But the verdict may have been based merely upon the ground that the plaintiff was not at fault for not having completed his contract, but was prevented from doing so by the wrongful conduct of the defendant. Was such a finding warranted ?

¶6*311The plaintiff contends that' the defendant on June 7 wrongfully refused to make a payment which he was then under obligation to make, and without which, as the defendant knew, the plaintiff could not go on with the work. This payment was not due under the terms of the original contract. But the plaintiff contended and testified that shortly after the contract was made he told the defendant that he, the plaintiff, had been disappointed in obtaining some money to use upon the work, and that it would be very hard for him to keep on with the contract; and that an oral agreement was then made between the parties, changing the terms of the written contract as to the payments to be made *by the defendant, so that the defendant should pay to the plaintiff the sum of $250 per week, if the payments thus to be made did not exceed the next instalment fixed by the contract. The defendant denied this assertion; the plaintiff’s testimony was somewhat weakened on cross-examination, and the auditor’s report did not fully sustain the contention; but the question was for the jury. They could find that the modification was made, and that it was made in consequence of the plaintiff’s statement to the defendant, which was understood by both parties to be in substance a statement that the plaintiff could not go on with his work and must and would abandon the contract unless it was modified. This makes it necessary under our decisions to say that the modification had, or could be found to have had, a good consideration, and that it was valid. Munroe v. Perkins, 9 Pick. 298. Holmes v. Doane, 9 Cush. 135. Peck v. Requa, 13 Gray, 407. Hastings v. Lovejoy, 140 Mass. 261, 264. Earnshaw v. Whittemore, 194 Mass. 187. Hanson & Parker v. Wittenberg, 205 Mass. 319, 324. Parrot v. Mexican Central Railway, ante, 184.

¶7It follows that the jury could find that the defendant did unjustifiably prevent the plaintiff from going on with his work under the written contract. They could find that the defendant’s refusal to make the payment due on June 7, or any future payments under the modified agreement, was not justified by the disputes that had arisen about plastering or the excavations to be made, or by the contention that the plaintiff’s woi-k had not been done to the defendant’s “ perfect satisfaction.” *312These words are no stronger than the expression “ entire satisfaction,” which was considered in Handy v. Bliss, 204 Mass. 513. The instructions given conformed to the rule laid down in that case, and were correct.

¶8These considerations make most of the defendant’s requests for instructions immaterial. So far as necessary, they are covered by what has been said.

¶9 Exceptions overruled.

/207/mass/304 · .json · Public domain