Public-domain · open source
OpenJurist
← 224 F.3d 1340 - Sauer Incorporated v. Richard J. Danzig, Secretary of the Navy

Sauer Incorporated v. Richard J. Danzig, Secretary of the Navy’s Empirical Analysis

2000

Citation profile

36
cited by 36 later decisions
2
states following
September 2020
most recently cited

1 district · 2 state decisions

How this case has been cited

Cited by 36 later decisions — most recently September 2020 · most notably George Sollitt Construction Co. v. United States (2005), Morganti National, Inc. v. United States (2001)

1 district · 2 state decisions

190200020102020decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

Relationships

Relies on Electronic & Missile Facilities, Inc. v. United States · Commerce International Co. v. United States · Blinderman Construction Co. v. United States · Paul Hardeman, Inc. v. United States · William F. Klingensmith, Inc. v. United States

Most-quoted passages

The sentences later courts lift from this opinion, ranked by how many decisions quote each — the parts of the opinion doing the work. These counts are smaller than the citation total above because most of the 36 citing decisions cite the case generally; a passage count includes only decisions quoting that exact language verbatim.

  1. “A contractor may seek an equitable adjustment to compensate for increased costs of performance flowing from changes that alter the work to be performed under the contract. To prevail on its claim for equitable adjustment(s), plaintiff must demonstrate first that any increased costs arose from conditions differing materially from those indicated in the bid documents, and that such conditions were reasonably unforeseeable in the light of all the information available to the contractor. Plaintiff must also show that its contract costs actually increased, and that the cost increases were the direct and necessary result of the change.”
    1 later decision quote this exact passage · from the majority
  2. “[T]he Contractor [shall not be] charged with damages under this clause, if — (1) the delay in completing the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor. Examples of such causes include ... (ii) acts of the Government in either its sovereign or contractual capacity ... (x) unusually severe weather....”
    1 later decision quote this exact passage · from the majority
  3. “show that a government-imposed delay occurred.”
    1 later decision quote this exact passage · from the majority

How this case has been treated — in progress

Whether each later court followed, distinguished, criticized, or overruled this decision. The treatment classification (task #35) runs highest-cited cases first and lights up here as it reaches this one.