Public-domain · open source
OpenJurist
← 227 Or. 299 - Collins v. POST

Collins v. POST’s Empirical Analysis

1961

Citation profile

10
cited by 10 later decisions
4
states following
October 2010
most recently cited

2 district · 8 state decisions

How this case has been cited

Cited by 10 later decisions — most recently October 2010

2 district · 8 state decisions

30196119701980199020002010decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

Most-quoted passages

The sentences later courts lift from this opinion, ranked by how many decisions quote each — the parts of the opinion doing the work. These counts are smaller than the citation total above because most of the 10 citing decisions cite the case generally; a passage count includes only decisions quoting that exact language verbatim.

  1. “The general rule is that one who contracts absolutely and unqualifiedly to erect a structure for a stipulated price enters into an entire contract to complete such work and must bear the losses resulting from its accidental destruction or damage before completion. The underlying theory is that destruction or damage of the subject matter is no legal justification for nonperformance of the contract unless the contract stipulates that he will not be responsible for losses occurring in such manner. Such a contractual immunity is not present here. 17A C.J.S. Contracts Sec. 466b, p. 961; 9 AmJur. 43, Building and Construction Contracts Sec. 60; Annotation, 53 A.L.R. 105 , 109. See, also, Savage v. Glenn, 10 Or. 440 .”
    1 later decision quote this exact passage

How this case has been treated — in progress

Whether each later court followed, distinguished, criticized, or overruled this decision. The treatment classification (task #35) runs highest-cited cases first and lights up here as it reaches this one.