Robinson v. United States’s Empirical Analysis

261 U.S. 486 · 1923

Citation profile

106
cited by 106 later decisions
12
cited 12 times by the Supreme Court
9
states following
July 2008
most recently cited

20 federal appellate · 3 district · 35 state decisions

How this case has been cited

Cited by 106 later decisions (12 by the Supreme Court) — most recently July 2008 · most notably Davis v. Department of Labor & Industries (1942), Priebe & Sons, Inc. v. United States (1947)

20 federal appellate · 3 district · 35 state decisions

190192319301940195019601970198019902000decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

Relationships

Relies on United States v. Spearin · Sun Printing Publishing Association v. William L Moore · United States v. Bethlehem Steel Co. · United States v. Atlantic Dredging Co. · Wise v. United States

Most-quoted passages

The sentences later courts lift from this opinion, ranked by how many decisions quote each — the parts of the opinion doing the work. These counts are smaller than the citation total above because most of the 106 citing decisions cite the case generally; a passage count includes only decisions quoting that exact language verbatim.

  1. ““.. . The fact that the Government’s action caused some of the delay, presents no legal ground for denying it compensation for loss suffered wholly through the fault of the contractor. Since the contractor agreed to pay a specified rate for each day’s delay not caused by the Government, it was clearly the intention that it should pay for some days’ delay at that rate, even if it were relieved from paying for other days, because of the Government’s action. If it had appeared that the first 61 days’ delay had been due wholly to the contractor’s fault, and the Government had caused the last 60 days’ delay, there could hardly be a contention that the provision for liquidated damages should not apply. Here the fault of the respective parties was not so clearly distributed in time; and it may have been difficult to determine, as a matter of fact, how much of the délay was attributable to each. But the Court of Claims has done so in this case. Its findings are specific and conclusive. . . . ” 261 U.S. at 488-489 , 43 S.Ct. at 421 .”
    4 later decisions quote this exact passage · from the majority
  2. “The case is wholly unlike United States v. United Engineering Co., . . . upon which claimant relies. The question there was one of construction. The lower court found, as a fact that, but for the government’s action, the work would have been completed within the contract period, and this court construed the provision for liquidated damages as not applicable to such a case. Here the question is not properly one of construction. Id. at 489, 43 S.Ct. at 400 .”
    1 later decision quote this exact passage · from the majority
  3. “shall be allowed one day, additional to the time herein stated, for each and every day of . . . delay [that may be caused by the Government]”
    1 later decision quote this exact passage · from the majority

How this case has been treated — in progress

Whether each later court followed, distinguished, criticized, or overruled this decision. The treatment classification (task #35) runs highest-cited cases first and lights up here as it reaches this one.