Public-domain · open source
OpenJurist

27 Ga. App. 431

Holmes v. Venable

Court of Appeals of Georgia

Decided October 7, 1921

Court of Appeals of Georgia · decided 1921-10-07

<p>1. Where a creditor of a contractor sued out garnishment against an owner of real estate who had employed the contractor to construct improvements thereon, and the owner answered not indebted, and where a mechanic employed by the contractor sought to intervene by traversing the answer, but failed to give bond to the plaintiff as provided by the Civil Code (1910), § 5282, and in consequence the traverse was dismissed on the creditor’s motion, and where the contractor filed, as a traverse of the garnishee’s answer, a denial of the debt and judgment alleged in the garnishment affidavit, which traverse was disallowed by agreement of counsel in the garnishment proceeding, and where the mechanic subsequently claimed a-nd caused to be recorded a lien upon the property of the owner, under sections 3352 and 3353 of the Civil Code, and, to enforce it,.brought suit jointly against the contractor and the owner, praying a general judgment against the contractor and a special lien against the property, a plea of res judicata by the owner, setting up the previous dismissal of the plaintiff’s traverse in the garnishment proceeding, as an adjudication against his rights, and the previous disallowance of the contractor’s traverse in that proceeding, as an adjudication that the owner was not liable, could not properly be sustained, since the dismissal of the plaintiff’s traverse because of his failure to give bond to the plaintiff in fi. fa. did not amount to an adjudication upon the question of indebtedness between any of the parties concerned. Gordon v. Wilson, 99 Ga. 354 (27 S. E. 762); Ware v. Laird, 93 Ga. 342 (20 S. E. 635). Moreover, the contractor, defendant in fi. fa., was not a party to such former proceeding on the issue of indebtedness between the creditor, plaintiff in fi. fa., and the owner garnishee. Leake v. Tyner, 112 Ga. 919 (38 S. E. 343) ; Teft v. Booth, 104 Ga. 590, 591 (30 S. E. 803).</p> <p>:2. Where a petition to enforce a mechanic’s lien under sections 3352 and 3353 of the Civil Code (1910) alleges that the plaintiff’s employer, a contractor, agreed with the owner “ to repair the premises ” of the latter, that the contractor, “ with the knowledge and consent ” of the owner, employed the plaintiff “ to work on said house in repairing said house under said contract,” that the plaintiff earned the sum sued for, “ working under said employment,” and that the contractor “ earned ” the amount sued for, or more,— “ a sufficient amount to pay petitioner,— which has not been paid,” and there is attached to the petition, as an exhibit, a copy of the contract between the owner and the contractor, showing that the work to be done was “ to refinish by rescraping, smoothing, filling, and polishing the entire first floor, except the cook-room, of the residence” of the owner, the facts alleged are sufficient to constitute the plaintiff a “ mechanic ” or laborer within the meaning of the statutes, and the petition is good as against a general demurrer.</p> <p>3. While there can be no valid judgment of foreclosure of a mechanic’s lien upon real estate improved, for labor done for a contractor employed by the owner, in the absence of a judgment in favor of the mechanic against the contractor, yet the contractor and the owner may be joined in one foreclosure suit, with prayers for a general judgment against the former and for the establishment of a special lien against the property. Columbian Iron Works v. Crystal Springs Bleachery Co., 145 Ga. 621 (1), 624 (89 S. E. 751); Griffin v. Gainesville Iron Works, 144 Ga. 840, 842 (88 S. E. 201); Mass. Bonding Co. v. Realty Trust Co., 142 Ga. 499 (5), 500 (83 S. E. 210).</p> <p>4. Where the evidence for the mechanic on his foreclosure is sufficient to authorize a finding that his particular part of the work has been properly performed for the contractor under the latter’s contract with the owner, and that the amount due the mechanic does not exceed the amount earned by the contractor under that contract, the mere fact that the owner may be able to show that the contractor has not performed his entire contract will not authorize a reversal of a judgment- setting up the mechanic’s lien.</p>

Key passage — most relied on by later courts

“in no event shall the aggregate amount of liens set up hereby exceed the contract price of the improvements made.”

quoted by 1 later decision, including 111 Ga. App. 733 - Scott v. Williams

Relies on Green v. Farrar Lumber Co. · Prince v. Neal-Millard Co. · Tuck v. Moss Manufacturing Co.

Good law ✅— No negative treatment on recordhow we know

Decided 1921-10-07

How this case has been cited

Cited by 10 later decisions — most recently December 1986

10 state decisions

401921193019401950196019701980decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

View the full empirical analysis of this case →

Jenkins, P. J.

¶1(After stating the foregoing facts.) The ruling upon the question as to whether the plaintiff is entitled to foreclose his lien until the contractor shall have first fully performed his obligations under his contract with the owner may properly be somewhat elaborated. It is the general rule that, where an owner of real estate engages a contractor to construct or improve a building thereon, and, under employment of the contractor, a mechanic perforins labor in constructing or improving the building, there is sufficient privity between the-mechanic and the owner to support a lien on the property. Logue v. Walker, 141 Ga. 644 (81 S. E. 849). But while the contract between the owner and the contractor furnishes the basis of the laborer’s or materialman’s lien, where the work is done or the material furnished upon the employment of the contractor, these liens are not entirely as of subrogation to the right of the contractor to his lien. Prince v. Neal-Millard Co., 124 Ga. 894, 884 (53 S. E. 761, 4 Ann. Cas. 615). The lien of such a mechanic is itself statutory, and is not affected by any private arrangement between the property owner and the contractor (Tuck v. Moss Mfg. Co., 127 Ga. 729 (2), 56 S. E. 1001); but it is subject to the exceptions and requirements imposed by the statute, such as that “ in no event shall the aggregate amount of liens set up hereby exceed the contract price of the improvements made.” Civil Code (1910), § 3352 (2). To this extent the statutory rights of the mechanic to his lien are controlled by the contract between the *434owner and the contractor, and the mechanic or laborer must show that the amount for which he asserts a lien comes, in whole or in part, within the contract price agreed between the contractor and the owner of the property improved. Stevens v. Ga. Land Co., 122 Ga. 317 (50 S. E. 100). Under the statute it is incumbent upon the owner to see that payments to the contractor are, to the full amount of the contract price, appropriated to outstanding claims of materialmen and laborers. Green v. Farrar Lumber Co., 119 Ga. 30 (46 S. E. 62). The owner may defend by showing that the lien “has been waived in writing,” by the material-man or mechanic, or that the owner has taken from the contractor the statutory affidavit that such material and labor claims have been paid, or that the money paid the contractor actually went to the discharge of liens created by the contractor in the purchase of material or the employment of labor. But he cannot defend against the suit of a mechanic or materialman to foreclose such a lien by showing that others are claiming liens against his property, and thus proving merely a possible or even probable future liability. Tuck v. Moss Mfg. Co., 127 Ga. 733 (supra).

¶2The lien of the mechanic and the procedure for its enforcement being statutorjr, it is not necessary to allege or prove that the contractor completed his contract with the owner; but the mechanic need only show a compliance on his part with the statute, and that he comes under its protection. Arnold v. Farmers Exchange, 123 Ga. 731, 733 (51 S. E. 754). Still he cannot, in any event, recover an amount greater than the amount for which the owner has become liable to the contractor under their contract; and thus it would seem that on a foreclosure of a mechanic’s lien the owner might be able to defend completely by showing that the contract was an entire one, and that the contractor, by abandoning his contract before its completion, has necessitated its completion through another contractor at an. amount exceeding the original contract price and therefore at a loss to the owner. Rowell v. Harris, 121 Ga. 239 (48 S. E. 948); Prince v. Neal-Millard Co., supra. The evidence does, not, however, bring the instant case within the exception made by this rule. Judgment affirmed.

Stephens and Hill, JJ., concur.
/27/gaapp/431 · .json · Public domain