¶1The center of gravity of this transaction may have been that plaintiff’s commission was to be paid for services to be rendered by him in the performance, rather than in the procurement, of this Government contract. A trial is necessary. Defendant’s motions for judgment on the pleadings and for summary judgment were properly denied. Order unanimously affirmed, with $20 costs and disbursements to the respondent. Present — Cohn, J. P,, Callahan, Van Voorhis and Breitel, JJ.
281 A.D. 880
Boylan v. Foremost Machine Builders, Inc.
Appellate Division of the Supreme Court of the State of New York
Decided March 31, 1953
Appellate Division of the Supreme Court of the State of New York · decided 1953-03-31
Decided 1953-03-31