Public-domain · open source
OpenJurist

31 F.4th 1349

Csi Aviation, Inc. v. Dhs

U.S. Courts of Appeals

Decided April 14, 2022

U.S. Courts of Appeals · decided 2022-04-14

Cited by 1 later decisions — most recently June 2025

Applies 28 U.S.C. § 1295

Relies on Community Heating & Plumbing Co. v. Kelso · Callaway Golf Co. v. Acushnet Co. · Northrop Grumman Information Technology, Inc. v. States

Good law ✅— No negative treatment on recordhow we know

Decided 2022-04-14

View the full empirical analysis of this case →

Case: 21-1630    Document: 49     Page: 1   Filed: 04/14/2022




   United States Court of Appeals
       for the Federal Circuit
                  ______________________

                  CSI AVIATION, INC.,
                       Appellant

                             v.

     DEPARTMENT OF HOMELAND SECURITY,
      GENERAL SERVICES ADMINISTRATION,
                    Appellees
             ______________________

                        2021-1630
                  ______________________

    Appeal from the Civilian Board of Contract Appeals in
 Nos. 6292/6386, 6543/6801, 6581/6582, Administrative
 Judge Kyle E. Chadwick, Administrative Judge Harold C.
 Kullberg, Administrative Judge Jerome M. Drummond.
                 ______________________

                  Decided: April 14, 2022
                  ______________________

     JASON NICHOLAS WORKMASTER, Miller & Chevalier
 Chartered, Washington, DC, argued for appellant. Also
 represented by ELIZABETH J. CAPPIELLO, LAURA G.
 FERGUSON, ALEJANDRO LUIS SARRIA.

    IN KYU CHO, Civil Division, Commercial Litigation
 Branch, United States Department of Justice, Washington,
 DC, argued for all appellees. Also represented by BRIAN M.
 BOYNTON, MARTIN F. HOCKEY, JR., PATRICIA M. MCCARTHY.
 Appellee Department of Homeland Security also
Case: 21-1630    Document: 49     Page: 2    Filed: 04/14/2022




 2                                   CSI AVIATION, INC.   v. DHS



 represented by CASSANDRA MAXIMOUS, ANDREW WAGNER,
 Office of the Principal Legal Advisor, United States Department of Homeland Security, Washington, DC. Appellee
 General Services Administration also represented by
 SARAH PARK, United States General Services Administration, Washington, DC.
                  ______________________

     Before NEWMAN, DYK, and HUGHES, Circuit Judges.
 HUGHES, Circuit Judge.
     This is a government contract case in which CSI Aviation, Inc. seeks payment from the Department of Homeland
 Security for flight cancellation charges, totaling
 $40,284,548.89, that CSI contends it is owed under the
 Schedule Contract. CSI appeals the decision of the Civilian
 Board of Contract Appeals holding that the CSI Terms and
 Conditions were not incorporated by reference into the
 Schedule Contract and dismissing six consolidated appeals
 on that basis. Because we determine that the Schedule
 Contract expressly incorporates at least one document that
 unambiguously identifies the CSI Terms and Conditions
 and that makes clear such terms and conditions apply to
 all operations, we reverse the Board’s holding to the contrary. Since that holding formed the basis for all six dismissals, we vacate the Board’s summary judgment decision
 and remand for further proceedings.
                              I
                              A
     Under the Federal Supply Schedule Program, the General Services Administration (GSA) “acts as the contracting
 agent for the federal government” and negotiates “base
 contracts with suppliers of commercial products and services.” Sharp Elecs. Corp. v. McHugh, 
707 F.3d 1367, 1369
 (Fed. Cir. 2013) (cleaned up). These base (or schedule) contracts streamline the acquisition process for federal
Case: 21-1630     Document: 49     Page: 3    Filed: 04/14/2022




 CSI AVIATION, INC.   v. DHS                                 3



 agencies, see CGI Fed. Inc. v. United States, 
779 F.3d 1346, 1352
 (Fed. Cir. 2015), and “allow [them] to take advantage
 of the flexible and dynamic commercial market-pricing environment,” so all federal customers, “regardless of size or
 location,” can “place orders directly with contractors and
 receive the same services, convenience, and pricing,”
 Appx5307.
      The Federal Supply Schedule Program “closely mirrors
 commercial buying practices.” Appx5307. But, instead of
 “evaluating prices head to head . . . in a competitive environment,” GSA assesses pricing “as it relates to [the offeror’s] commercial selling practices.” Appx8775. An offeror
 submits a completed commercial sales practices sheet
 along with supporting documentation that discloses commercial pricing, market participants, sell price, and terms
 and conditions for the offeror’s “most favored customer” in
 a competitive environment. Appx5367, 8775. Relying on
 this information and in accordance with the Federal Acquisitions Regulations (FAR), a GSA contracting officer determines whether the pricing is “fair and reasonable” not as it
 relates to the competitive environment but “as it relates to
 [the offerror’s] commercial selling practices.” Appx5367,
 8775. Should the contracting officer accept the offer, the
 Federal Supply Schedule Program “allow[s] executive
 agencies to issue orders for those commercial products pursuant to the underlying [GSA] contract.” CGI Fed., 
779 F.3d at 1352
.
                               B
      CSI Aviation, Inc. is a worldwide services broker that
 provides “passenger and cargo air charter, aircraft leasing,
 and comprehensive aircraft management.” Appx6924. On
 November 6, 2008, CSI submitted an offer to GSA for a
 Travel Services Solutions contract under Schedule 599 for
 “[a]ir charter services operated by brokers, and various
 auxiliary services that will be used to support the contract.”
 Appx6924. Under this contract, CSI would “provide a full
Case: 21-1630    Document: 49      Page: 4    Filed: 04/14/2022




 4                                    CSI AVIATION, INC.   v. DHS



 range of services to assist Government agencies in Travel
 Services Solutions” through “a non-mandatory, indefinite
 delivery - indefinite quantity Multiple Award Schedule
 contract that [would] allow for firm fixed-price task orders
 (and for labor hours and time and materials task orders
 based on firm-fixed prices).” Appx6924.
      On February 27, 2009, in response to a revised solicitation from GSA for new air charter services, CSI submitted
 a revised proposal. This proposal included its commercial
 price list and the CSI Terms and Conditions, dated February 2009. In its March 2, 2009 response, the Contracting
 Officer asked CSI to provide model numbers for each aircraft offered because the provided aircraft types were “too
 vague to do a proper comparative price analysis.”
 Appx9055. The Contracting Officer also acknowledged that
 “the CSI Terms and Conditions document [had been] submitted to [GSA]” but asked CSI if GSA was “required to
 initial off on these or are these requirements for ordering
 agencies to comply with? If so,” the Contracting Officer continued, he was “going to have to submit these for Legal review as we haven’t had to agree to terms like these from
 other air charter providers.” Appx9055. CSI replied that
 “the Terms and Conditions . . . were just provided for
 [GSA’s] information.” Appx9581.
     On March 9, 2009, the Contracting Officer “determined
 that CSI’s offer, including the revised pricing (March 2,
 2009), [was] acceptable to the Government.” Appx9592. He
 instructed CSI to review a document that would “become
 the attachment to the signed cover page [Standard
 Form] 1449” and to “confirm that this accurately and completely addresse[d] all elements of the contract to be
 awarded that may not be directly addressed within the information submitted and/or agreed upon.” Appx9592. CSI
 immediately returned “the final documents [the parties]
 ha[d] agreed to,” including the SF1449 attachment, a final
 proposal letter, and the Revised Commercial Price List, all
 of which CSI dated March 9, 2009 to reflect the final review
Case: 21-1630     Document: 49     Page: 5    Filed: 04/14/2022




 CSI AVIATION, INC.   v. DHS                                5



 date. Appx9592. GSA awarded the Schedule Contract to
 CSI the next day.
                               C
     CSI’s Schedule Contract includes the signed SF1449
 and attached pages, Appx5277–79, together with the following documents, among others, listed in the SF1449 as
 being expressly “incorporated and made a part of the contract”: 1) the Travel Services Solutions schedule solicitation “dated February 10, 2009, superseding the former
 solicitation”; 2) the Offer; and 3) the Revised Commercial
 Price List, Appx5279 (listing the named documents on
 page 1b of CSI’s SF1449).
     The Offer’s table of contents contains a “Pricing” section that identifies four documents submitted as part of the
 Offer, including: “CSI Commercial Sales Practices,” “CSI
 Pricing Policy,” the Revised Commercial Price List, and
 “CSI Terms and Conditions (Standard Commercial Warranty).” Appx5289. The Pricing Policy includes a “Terms
 and Conditions” provision stating that “CSI Terms and
 Conditions, in other words, our Standard Commercial Warranty, will apply to all operations and are included for reference . . . . Pricing conditions are further detailed in our
 CSI Commercial Pricelist.” Appx5516.
     The Revised Commercial Price List provides the total
 hourly rates for Special Item Number 599-5 (air charter
 broker services), where the “[h]ourly prices include aircraft, crew, maintenance, insurance, fuel and domestic
 ground handling” and represent the highest possible
 hourly rate that the government could be charged.
 Appx5297–98. For Special Item Number 599-1000 (contract support items, and auxiliary supplies and services),
 the Revised Commercial Price List states: “Hourly prices
 do not include other charges below,” referring to a bulletpoint list that identifies specific taxes, fees, surcharges,
 and other charges that “will be determined for each requirement, if applicable.” Appx5298–99 (emphasis
Case: 21-1630     Document: 49      Page: 6    Filed: 04/14/2022




 6                                     CSI AVIATION, INC.   v. DHS



 omitted). And “[a]ny charges will be itemized for each requirement and are subject to change in accordance with our
 CSI Terms and Conditions.” Appx5298. The Revised Commercial Price List also includes a “Terms and Conditions”
 provision, which states that “CSI Terms and Conditions
 02/09, or most current, will apply to all operations.”
 Appx5299.
     On February 27, 2009, CSI emailed its Commercial
 Price List and the CSI Terms and Conditions to the GSA
 Contracting Officer. 1 The CSI Terms and Conditions include a “Cancellation Charges” provision that states:
     In addition to any damages, CSI and the Air Carrier shall be entitled to recover any special out of
     pocket expenses actually incurred specifically, directly and solely in connection with the cancelled
     flights. . . . If no cancellation charges are set forth
     on the first page of this Agreement, then a 25%
     non-refundable cancellation charge will apply for
     up to 14 days prior to flights, and 100% cancellation
     charge will apply if less than 14 days prior to
     flights.
 Appx9031.



     1    CSI emailed its Commercial Price List to the GSA
 Contracting Officer on February 27 and then again sent its
 Revised Commercial Price List to the Contracting Officer
 on March 9, 2009. See Appx9024, 9592. Both versions of the
 price list include a “Terms and Conditions” provision, but
 the Revised Commercial Price List identifies the specific
 version of the CSI Terms and Conditions by date. Compare
 Appx9028 (Original Commercial Price List: “CSI Terms
 and Conditions with GSA[] will apply to all operations.”),
 with Appx9599 (Revised Commercial Price List: “CSI
 Terms and Conditions 02/09, or most current, will apply to
 all operations.”); see also Appx5299.
Case: 21-1630     Document: 49     Page: 7    Filed: 04/14/2022




 CSI AVIATION, INC.   v. DHS                                7



                               D
     In 2014, U.S. Immigration and Customs Enforcement
 awarded CSI five task orders—four on March 27, 2014, and
 one on June 2, 2014—through the Schedule Contract for
 performance of removal missions out of five domestic airport hubs. Including all options and extensions, the orders’
 performance periods extended through June 30, 2018.
      In June 2017, ICE canceled a scheduled removal flight
 and “CSI incurred a deposit loss of approximately $600k
 with [the airline provider] due to the short notice cancellation by ICE.” Appx86. The ICE Contracting Officer admitted that the agency was “liable to CSI for the loss of the
 deposit” in accordance with “the terms of CSI’s GSA contract,” i.e., the Schedule Contract, and its task order with
 ICE. Appx86–87. The ICE Contracting Officer agreed, on
 behalf of the agency, to pay a cancellation fee. Appx87. The
 Contracting Officer acknowledged that “[t]he GSA contract
 [i.e., the Schedule Contract] T&Cs says, ‘CSI Terms and
 Conditions will apply to all operations.’” Appx85. At the
 CO’s request, CSI shared a copy of the CSI Terms and Conditions with the agency.
     Then, on December 7, 2017, CSI tried to perform another removal mission—this one, to Somalia—but it was
 unsuccessful and returned to the United States the next
 day. ICE scheduled a replacement removal mission, with
 an estimated duration of 39.25 hours at $25,065.00 per
 flight hour, for December 20, 2017. But, on December 19,
 2017, the scheduled flight’s passengers successfully obtained a temporary restraining order enjoining ICE from
 removing them. ICE immediately informed CSI and canceled the scheduled flight. Consequently, CSI invoiced ICE
 for the total estimated amount for the cancelled removal
 mission to Somalia, totaling $983,801.25. And, on February 7, 2018, the ICE Contracting Officer “reject[ed] the invoice in full because the services were not provided and no
 flight hours were flown.” Appx121.
Case: 21-1630     Document: 49      Page: 8    Filed: 04/14/2022




 8                                     CSI AVIATION, INC.   v. DHS



                               1
     On November 30, 2018, CSI submitted a certified claim
 to the GSA CO 2 for payment of the invoice amount. The
 Contracting Officer found that the “Schedule Contract had
 incorporated the CSI Terms and Conditions, including a
 cancellation clause, providing that a 100% cancellation
 charge would apply if the cancellation occurred within fourteen (14) days of a scheduled flight.” Appx10185. But the
 Contracting Officer concluded that it could not grant the
 relief CSI sought since “GSA does not have the authority to
 grant the monetary relief . . . as [it has] no authority to either pay the liability of another agency or order ICE to pay
 any amounts that may be owed.” Appx10185.
     CSI submitted another certified claim to the GSA Contracting Officer on April 26, 2019, this time for payment of
 45 overdue invoices tendered between December 14, 2018,
 and February 7, 2019. See Appx1326–29 (listing the invoices, corresponding task orders, amounts due, and pertinent dates for each invoice). “The amounts [c]laimed in all
 the [i]nvoices, collectively totaling $40,284,548.89, equal
 the sum value of dozens of aircraft transportation charters . . . purchased by ICE and subsequently cancelled by
 ICE less than 14 days before the flights were performed.”
 Appx1322. While the Contracting Officer again found that


     2   CSI also submitted a certified claim for payment of
 the same invoice to the ICE Contracting Officer on July 25,
 2018. But only the GSA Contracting Officer can resolve a
 contractor’s claims that involve any contract interpretation
 dispute associated with the Schedule Contract. See Sharp
 Elecs. Corp. v. McHugh, 
707 F.3d 1367, 1373
 (Fed. Cir.
 2013) (“[W]e conclude that the FAR creates a bright-line
 rule—all disputes requiring interpretation of the schedule
 contract go to the schedule CO, even if those disputes also
 require interpretation of the [agency task] order, or involve
 issues of performance under the [task] order.”).
Case: 21-1630     Document: 49     Page: 9    Filed: 04/14/2022




 CSI AVIATION, INC.   v. DHS                                 9



 the CSI Terms and Conditions were “incorporated into the
 contract,” it also found that the cancellation charges, “located within [the CSI] Terms and Conditions, [were] directly in conflict with the FAR 52.212-4(l) Termination for
 the Government’s Convenience [C]lause (hereinafter ‘Termination Clause’), which is required in all GSA [schedule]
 contracts.” Appx10192 (footnote omitted). The Contracting
 Officer explained that since the CSI Terms and Conditions
 “were an attachment to the contract buried within its 2008
 offer submission,” the incorporated document “fall[s] to the
 eighth level . . . when establishing precedence.”
 Appx10193. The Contracting Officer decided that the “Termination Clause takes precedence over CSI’s Commercial
 Terms and Conditions, and, particularly, its Cancellation
 Charges.” Appx10192–93.
                               2
     CSI appealed the Contracting Officer’s decisions to the
 Board and the Board found, on summary judgment, that
 the Schedule Contract did not incorporate the CSI Terms
 and Conditions by reference. The Board saw “at least three
 problems with CSI’s arguments in favor of incorporation.”
 Appx8.
     First, the Board found significant the fact that the
 SF1449 expressly “incorporated and made part of the contract” a list of six documents and that “the CSI Terms and
 Conditions never appeared in that list.” Appx8. The Board
 faulted CSI for not using such express incorporation language for the CSI Terms and Conditions. Second, the Board
 found that the phrase “will apply to all operations,” used in
 the Commercial Price List to refer to the CSI Terms and
 Conditions, was “not the type of phrase that should be read
 as expressly incorporating fully into the contract some extrinsic text containing additional contract terms.” Appx9
 (cleaned up) (quoting Northrop Grumman Info. Tech., Inc.
 v. United States, 
535 F.3d 1339, 1347
 (Fed. Cir. 2008)). In
 the Board’s view, “these first two flaws . . . suffice to show
Case: 21-1630    Document: 49      Page: 10    Filed: 04/14/2022




 10                                   CSI AVIATION, INC.   v. DHS



 that the CSI Terms and Conditions were not incorporated
 in the schedule contract.” Appx9. Still, the Board identified
 a third flaw that, it believed, also rendered CSI’s position
 unavailing: “the residual ‘ambiguity about the identity of
 the document being referenced.’” Appx10 (quoting
 Northrop, 
535 F.3d at 1344
). There was “nothing in the text
 of the schedule contract” by which the Board “could . . . locate without doubt the ‘most current’ version of the CSI
 Terms and Conditions at any junction from March 2009 to
 2019.” Appx10.
     The Board granted the government’s summary judgment motion on January 4, 2021, after concluding that the
 Schedule Contract did not incorporate the CSI Terms and
 Conditions. The parties then filed a joint motion on January 27, 2021, stating “that they agree that the Board’s January 4, 2021[] decision on a contract interpretation issue
 common to [CSI’s] six appeals suffices to support denying
 the appeals” and asking the Board “to consolidate the appeals for the purpose of issuing one final and appealable
 decision.” Appx13. The next day, the Board granted the motion, consolidated the six appeals, and denied those appeals
 based on its January 4, 2021 decision.
    CSI timely appeals. We have jurisdiction under 
28 U.S.C. § 1295
(a)(10).
                              II
     The issue on appeal is whether the CSI Terms and Conditions are incorporated into the Schedule Contract by reference. This is a question of law we review de novo.
 Northrop, 
535 F.3d at 1343
.
                              A
     Incorporation by reference “provides a method for integrating material from various documents into a host document . . . by citing such material in a manner that makes
 clear that the material is effectively part of the host document as if it were explicitly contained therein.” Zenon
Case: 21-1630     Document: 49     Page: 11     Filed: 04/14/2022




 CSI AVIATION, INC.   v. DHS                                 11



 Env’t, Inc. v. U.S. Filter Corp., 
506 F.3d 1370, 1378
 (Fed.
 Cir. 2007) (alteration in original) (citation omitted). To incorporate material by reference, “the incorporating contract must use language that is express and clear, so as to
 leave no ambiguity about the identity of the document being referenced, nor any reasonable doubt about the fact
 that the referenced document is being incorporated into the
 contract.” Northrop, 
535 F.3d at 1344
. Said differently, “the
 language used in a contract to incorporate extrinsic material by reference must explicitly, or at least precisely, identify the written material being incorporated and must
 clearly communicate that the purpose of the reference is to
 incorporate the referenced material into the contract (rather than merely to acknowledge that the referenced material is relevant to the contract, e.g., as background law or
 negotiating history).” 
Id. at 1345
; see also Callaway Golf
 Co. v. Acushnet Co., 
576 F.3d 1331, 1346
 (Fed. Cir. 2009)
 (A “mere reference to another [document] is not an incorporation of anything therein.” (citation omitted)).
     Here, the Schedule Contract incorporates the Offer
 submitted by CSI during contract negotiations. Neither
 party disputes that this document was “made a part of the
 contract.” Appx5279. Rather, they disagree as to whether
 the Offer uses sufficient language to incorporate the CSI
 Terms and Conditions into the Schedule Contract by reference. We conclude that it does.
     The Offer plainly identifies the CSI Terms and Conditions—along with the CSI Commercial Sales Practice attachment, its Pricing Policy, and its Commercial Price
 List—in the “Pricing” section of its table of contents.
 Appx5289. And the Offer’s Pricing Policy contains a “Terms
 and Conditions” provision that expressly states, “CSI
 Terms and Conditions . . . will apply to all operations and
 are included for reference.” Appx5516. True to its word, a
 copy of the CSI Terms and Conditions, dated November
 2008, is included as part of the Offer. See Appx5525–27.
 Thus, the Offer makes clear the identity of the document
Case: 21-1630    Document: 49      Page: 12    Filed: 04/14/2022




 12                                   CSI AVIATION, INC.   v. DHS



 being referenced: the document titled “CSI Terms and Conditions.” And, as evidenced by the “Terms and Conditions”
 provision in the Offer’s Pricing Policy—which expressly
 employs “will apply to all operations” language—the referenced CSI Terms and Conditions apply to at least CSI’s
 pricing terms. Apply, Black’s Law Dictionary (11th ed.
 2019) (defining “apply” to mean “[t]o employ for a limited
 purpose” or “[t]o put to use with a particular subject matter”). We accordingly hold that the Offer uses sufficiently
 clear and express language to establish the identity of the
 document being referenced and to incorporate the CSI
 Terms and Conditions into the Schedule Contract by reference.
                               B
     In addition, none of the “flaws” the Board identified
 otherwise provides a proper basis for its decision holding
 that the Schedule Contract does not incorporate the CSI
 Terms and Conditions by reference. See Appx8–10.
     First, the Board placed too much weight on the fact
 that the Schedule Contract includes express language to
 incorporate some documents—like the Offer—and erroneously faulted CSI for not “us[ing] the same or similar language” to incorporate the CSI Terms and Conditions into
 the contract. Appx8. The Board reasoned that CSI’s use of
 such language to incorporate some documents “demonstrate[d] that the parties were familiar with language of
 incorporation and likely would have used the same or similar language had there been an intention to incorporate
 [the CSI Terms and Conditions] into the contract.” Appx8
 (cleaned up). In the Board’s view, the absence of such incorporation language “at least raises doubt about whether
 they intended to incorporate the CSI Terms and Conditions.” Appx8–9. But while the parties’ use of explicit incorporation by reference language conveys familiarity with
 contract language of incorporation, “[o]ur circuit . . . does
 not require ‘magic words’ of reference or of incorporation,”
Case: 21-1630     Document: 49     Page: 13    Filed: 04/14/2022




 CSI AVIATION, INC.   v. DHS                                13



 Northrop, 
535 F.3d at 1346
, and the Board offers no basis
 for why it relies on this as one of two dispositive reasons
 for finding no incorporation by reference. Indeed, even in
 Northrop, the opinion on which the Board relies, we treated
 the parties’ familiarity with language of incorporation as a
 mere footnote that bolstered our independently established
 conclusion. 
Id.
 at 1347 n.1.
     Second, the Board improperly determined that the
 “will apply to all operations” language—used to incorporate
 the CSI Terms and Conditions into the Schedule Contract—was “not the type of phrase that should be read as
 expressly incorporating fully into the contract some extrinsic text containing additional contract terms.’” Appx9
 (cleaned up). According to the Board, “[n]o language in the
 price list advises a reader to consult any other document to
 find additional prices, and ‘all operations’ does not unambiguously mean ‘all other pricing issues.’” Appx9. The
 Board said that “[i]t could mean that, but it could alternatively refer to something else, such as logistical operations.” Appx9. The Board, however, offered no basis for its
 decision. It asserted only that it had “already ruled that
 this [language] was ambiguous” and that it saw “no reason
 to change [its] view.” Appx9. But the Board had never made
 such a ruling. It had found merely that the “all operations”
 language did “not unambiguously mean ‘all other pricing
 issues,’” and it had suggested that “it could alternatively
 refer to something else, such as logistical operations.”
 Appx9 (quoting Appx20). Indeed, the Board had expressly
 observed that it could not “interpret what the commercial
 price list may say about terminating or cancelling an order
 without learning more about the context of the contract language.” Appx20–21 (emphasis added). Yet in its later decision now on appeal, the Board disregarded any such
 context. This was error. And when we consider such “context” here, it becomes clear that the Board’s suggestion—
 that “all operations” could alternatively refer to “logistical
 operations”—is not a reasonable one. That an
Case: 21-1630    Document: 49      Page: 14    Filed: 04/14/2022




 14                                   CSI AVIATION, INC.   v. DHS



 interpretation of a contract term “is conceivable[] does not
 necessarily render that [term] ambiguous.” Cmty. Heating
 & Plumbing Co., Inc. v. Kelso, 
987 F.2d 1575, 1579
 (Fed.
 Cir. 1993).
      Third, the Board found that “CSI still could not prevail,
 due to the residual ‘ambiguity about the identity of the document being referenced,’” describing the CSI Terms and
 Conditions as “a moving target or, to be more charitable, a
 living document.” Appx9–10 (citation omitted). The Board
 faulted CSI for “choosing not to reveal the ‘most current’
 version of the CSI Terms and Conditions to the Government on a continuous basis” and concluded that, as a result, “CSI created ‘ambiguity about the identity of the
 document being referenced’ and defeated its own aim.”
 Appx11. We cannot agree. The language the Board refers
 to here derives from the Revised Commercial Price List’s
 “Terms and Conditions” provision: “CSI Terms and Conditions 02/09, or most current, will apply to all operations.”
 Appx5299. Even if there is a dispute as to which version
 controls, resolving that dispute is not relevant to deciding
 the question before us: whether any version was incorporated into the contract by reference. 3 The proper inquiry is



      3   We find problematic the Board’s seeming presumptions that there are uncountable versions of the CSI Terms
 and Conditions between 2009 and 2019 and that all such
 versions are pertinent to the parties’ contract dispute. In
 our view, the Board’s resolution should account for the effective date of the Schedule Contract, March 10, 2009.
     Replacing conjecture with record evidence, we note
 that there are only two relevant versions of the CSI Terms
 and Conditions found in the record: one dated November
 2008, the other February 2009, and both dated before the
 contract’s effective date. These versions include identical
 language addressing cancellation charges. Compare
Case: 21-1630     Document: 49       Page: 15   Filed: 04/14/2022




 CSI AVIATION, INC.   v. DHS                                15



 whether the Schedule Contract employs express and clear
 language, “so as to leave no ambiguity about the identity of
 the document being referenced, nor any reasonable doubt
 about the fact that the referenced document is being incorporated into the contract.” Northrop, 
535 F.3d at 1344
.
     The Board unreasonably strained to find ambiguity regarding the identity of the referenced document. The Offer
 expressly identifies the document titled “CSI Terms and
 Conditions” and unambiguously states that such document
 will apply to all operations. The Offer’s incorporation language, found in its Pricing Policy’s “Terms and Conditions”
 provision, refers to the “CSI Terms and Conditions” document that was also included as part of the Offer.
                               III
      Because the Schedule Contract, through the incorporated Offer, unambiguously identifies the CSI Terms and
 Conditions and specifies that such terms and conditions
 will apply to all operations, we hold that the Schedule Contract incorporates the CSI Terms and Conditions by reference. We therefore reverse the Board’s holding to the
 contrary. And since the Board’s holding was the basis for
 its decision to grant summary judgment and dismiss six
 consolidated appeals, we vacate that decision and remand
 for further proceedings. In doing so, we do not foreclose the



 Appx5527 ¶ 16(C) (November 2008 version: “[A] 25% non-refundable cancellation charge will apply for up to 14 days
 prior to flights, and 100% cancellation charge will apply if
 less than 14 days prior to flights.”), with Appx9031 ¶ 16(C)
 (February 2009 version: “[A] 25% non-refundable cancellation charge will apply for up to 14 days prior to flights, and
 100% cancellation charge will apply if less than 14 days
 prior to flights.”). We see no basis for the Board to unreasonably strain to find ambiguity between identical copies
 of the cancellation charges provision.
Case: 21-1630    Document: 49     Page: 16     Filed: 04/14/2022




 16                                   CSI AVIATION, INC.   v. DHS



 possibility of finding the CSI Terms and Conditions inapplicable for some other reason or that the cancellation provision is inconsistent with other provisions in the contract,
 such as the Termination Clause, but we leave any such possibility for the parties to raise and the Board to decide on
 remand.
      VACATED IN PART, REVERSED IN PART, AND
                    REMANDED
                            COSTS
 No costs.

/31/f4th/1349 · .json · Public domain