P.J. Dick Inc. v. Principi’s Empirical Analysis
324 F.3d 1364 · 2003
Citation profile
3 federal appellate · 2 district · 5 state decisions
Relationships
Relies on Wickham Contracting Co. v. Fischer · Blinderman Construction Co. v. United States · Kearns v. Chrysler Corp. · Interstate General Government Contractors, Inc. v. West · E.R. Mitchell Construction Co. v. Danzig
Most-quoted passages
The sentences later courts lift from this opinion, ranked by how many decisions quote each — the parts of the opinion doing the work. These counts are smaller than the citation total above because most of the 28 citing decisions cite the case generally; a passage count includes only decisions quoting that exact language verbatim.
“approximately one quarter of the entire scope of the contract work”
3 later decisions quote this exact passage · from the majority“The damages at issue are damages which are awarded, pursuant to Eichleay, to a government contractor who suffers unabsorbed home office overhead when the government delays work on the contract indefinitely but requires the contractor to remain available to resume work immediately on the government's instruction. The rationale for such damages is explained, thusly: Home office overhead costs are those [costs] that are expended for the benefit of the whole business, which by their nature cannot be attributed or charged to any particular contract. They are fixed costs that are allocated on a pro-rata basis among various contracts. When the government delays or disrupts contract performance, the contractor's stream of income decreases while the fixed costs allocated to that contract continue. The Eichleay formula "seeks to equitably determine allocation of unabsorbed overhead to allow fair compensation of a contractor for government delay. . . ." Entitlement to Eichleay damages depends on proof of three elements: (1) a government-imposed delay occurred; (2) the government required the contractor to "standby" during the delay; and (3) while "standing by," the contractor was unable to take on additional work. Once the contractor proves the first two elements, a prima facie case of entitlement to Eichleay damages is established, the burden of production then shifts to the government to show either (1) that it was not impractical for the contractor to obtain `replacement work' during”
2 later decisions quote this exact passage · from the majority“[A] court evaluating a contractor’s claim for Eichleay damages should ask the following questions: (1) was there a government-caused delay that was not concurrent with another delay caused by some other source; (2) did the contractor demonstrate that it incurred additional overhead (i.e., was the original time frame for completion extended or did the contractor satisfy the Interstate three-part test [for establishing an early completion delay claim]); (3) did the Government CO issue a suspension or other order expressly putting the contractor on standby; (4) if not, can the contractor prove there was a delay of indefinite duration during which it could not bill substantial amounts of work on the contract and at the end of which it was required to be able to return to work on the contract at full speed and immediately; (5) can the government satisfy its burden of production showing that it was not impractical for the contractor to take replacement work (ie., a new contract) and thereby mitigate its damages; and (6) if the government meets its burden of production, can the contractor satisfy its burden of persuasion that it was impractical for it to obtain sufficient replacement work.”
1 later decision quote this exact passage · from the majority
How this case has been treated — in progress
Whether each later court followed, distinguished, criticized, or overruled this decision. The treatment classification (task #35) runs highest-cited cases first and lights up here as it reaches this one.