John P. CHAVERS, Plaintiff-Appellee, v. KURY CONSTRUCTION COMPANY, Defendant-Appellant.

Louisiana Court of Appeal

Decided October 13, 1978.

Louisiana Court of Appeal · decided 1978-10-13

Key passage — most relied on by later courts

“" A judgment of default must be confirmed by proof of the demand sufficient to establish a prima facie case. If no answer is filed timely, this confirmation may be made after two days, exclusive of holidays, from the entry of the judgment of default. When the demand is for a sum due on an open account, an affidavit of the correctness thereof shall be prima facie proof. When the demand is based upon a negotiable instrument, no proof of any signature thereon shall be required."”

quoted by 2 later decisions, including 377 So. 2d 532 - VILLE PLATTE CONCRETE SERV., INC. v. Western Cas. & Sur. Co., 479 So. 2d 1025 - Demars v. Luneau Mobile Home Sales, Inc.

“" All agreements relative to movable property, and all contracts for the payment of money, where the value does not exceed five hundred dollars, which are not reduced to writing, may be proved by any other competent evidence; such contracts or agreements, above five hundred dollars in value, must be proved at least by one credible witness, and other corroborating circumstances. "”

quoted by 1 later decision, including 377 So. 2d 532 - VILLE PLATTE CONCRETE SERV., INC. v. Western Cas. & Sur. Co.

Relies on Ascension Builders, Inc. v. Jumonville · 342 So. 2d 661 - Samuels v. Firestone Tire & Rubber Co. · 207 So. 2d 807 - Dodd v. Schell

Good law ✅— No negative treatment on recordhow we know

Decided 1978-10-13

How this case has been cited

Cited by 4 later decisions — most recently April 1990

4 state decisions

20197819801990decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

View the full empirical analysis of this case →

¶1Edwards, Stefanski & Barousse by Homer E. Barousse, Jr., Crowley, for defendant-appellant.

¶2Everett & Everett by Charles T. Everett, Crowley, for plaintiff-appellee.

¶3Before WATSON, GUIDRY and FORET, JJ.

¶4WATSON, Judge.

¶5Plaintiff, John P. Chavers, brought this suit against defendant, Kury Construction Company, alleged to be a Louisiana corporation, seeking: cancellation of a construction contract; a mandatory injunction commanding Kury to remove a concrete slab installed on Chavers' property; and the sum of $3,942.65 as damages.

¶6*951 Chavers alleged that he entered into a contract with Kury Construction Company for the construction of a residence on a lot in "Acadian Acres," a subdivision near Crowley, Louisiana, and, because defendant Kury laid a concrete slab on the lot in violation of a building restriction requiring dwellings to be placed at least 50 feet from the front property line[1], Rayne Building & Loan Association denied Chavers a loan.

¶7A default judgment was confirmed on January 3, 1978. The judgment issues a permanent injunction ordering defendant to remove the concrete slab on plaintiff's lot[2]; decrees that defendant be liable for "any damages" by virtue of a certain laborer's and materialman's lien[3]; and nullifies "any contract between plaintiff and defendant. . ." for the construction of the residence. Defendant Kury has appealed.

¶8The proof required for a confirmation of default is provided by LSA-C.C.P. art. 1702:

"A judgment of default must be confirmed by proof of the demand sufficient to establish a prima facie case. If no answer is filed timely, this confirmation may be made after two days, exclusive of holidays, from the entry of the judgment of default. …"

¶9The record does not reveal whether the contract between the parties was oral or written. If reduced to writing, the writing itself is the required proof. Ascension Builders, Inc. v. Jumonville, 262 La. 519, 263 So.2d 875 (1972). If oral, the proof sufficient to establish a prima facie case must meet the specific requirements for proving verbal contracts. Dodd v. Schell, 207 So.2d 807 (La.App. 4 Cir. 1968).

LSA-C.C. art. 2277 provides as follows:
"All agreements relative to movable property, and all contracts for the payment of money, where the value does not exceed five hundred dollars, which are not reduced to writing, may be proved by any other competent evidence; such contracts or agreements, above five hundred dollars in value, must be proved at least by one credible witness, and other corroborating circumstances."

¶10The only evidence presented at the confirmation hearing was plaintiff's testimony, together with copies of a lien filed by Pauline Lumber Company, Inc., and the restrictions on the lot.

¶11A plaintiff may fulfill the requirement of one credible witness, and the phrase "other corroborating circumstances" in Article 2277 does not require independent proof of every detail of a witness' testimony. Samuels v. Firestone Tire & Rubber Co., 342 So.2d 661 (La. 1977). However, in the instant case, the evidence does not furnish a basis for the trial court's finding that a contract existed between plaintiff and defendant. Kury Construction Company was not mentioned in plaintiff's testimony. During direct examination, plaintiff was asked:

"Q. Did you ever talk to Mr. Jack Kury about building a house?
"A. I only took a paper from the Homestead saying I could require the loan providing that he would build the house to specifications without making any changes in putting up the house." (TR. 22).

¶12This testimony is insufficient to establish a contractual relationship between plaintiff and Kury Construction Company, and there is no corroborating evidence to prove such a contract.

¶13It is therefore ordered that the judgment of the trial court be annulled and set aside. This case is remanded for a new trial in accord with the views expressed herein.

¶14Costs of the appeal are taxed against plaintiff.

¶15JUDGMENT ANNULLED: CASE REMANDED.

NOTES

¶16[1] According to Chavers' testimony, the concrete slab was placed 38 feet from the front property line.

¶17[2] We express no opinion on the provisions of the judgment entered by the trial court since the judgment is being set aside. See LSA-C.C.P. art. 3601.

¶18[3] See footnote (2) above.