¶1This is an action instituted by appellant on the bond of appellee James P. Karr, to recover damages for a breach of a contract for the construction of -a ditch in White county, Indiana, under and pursuant to the act of 1881 (Acts 1881, p. 410) and amendments thereto. §§5656-5615 Burns 1901.
¶2From the complaint it appears that various steps were taken before the Board of Commissioners of the County of *121White, under and pursuant to said act, for the establishment and construction of a certain public ditch, whereby on April 8, 1901, appellee Karr, being the lowest and best bidder for the construction of certain parcels of such ditch, the same was awarded to him, and he then and there entered into a contract with Jasper L. Ackerman, as auditor of said county, for the construction thereof. At the same time, and for the purpose of securing a full performance of such contract, he executed a bond payable to the State, in a sum double the amount of the contract price for such work, with Abram Sluyter as surety thereon, which bond was duly approved by said auditor, and is still in full force and effect. Said Karr has failed and refused to carry out his part of the contract, and to construct the ditch as therein provided. Relator by reason of such refusal was compelled to, and did thereafter, relet said contract to another at a cost or price of $1,000 more than the sum for which appellee Karr, by his said contract, agreed to do said work. Such subsequent contract was made at the lowest price for which relator could obtain such work to be done. Neither of the contracts aforesaid was for a contract price in excess of the estimated cost of such work, as reported by the viewers and reviewers of such ditch. By reason of appellee Karr’s failure to perform said work, and carry out his said contract as therein provided, relator says he was and is damaged in the sum of $1,000. He is prosecuting this suit for the benefit of the landowners whose lands have been assessed for the construction of said ditch. Judgment for $1,000 is demanded. Appellees demurred to the complaint on the grounds : (1) That relator has no legal capacity to sue, (2) that there is a defect of parties plaintiff, and (3) that the complaint does not state facts sufficient to constitute a cause of action. This demurrer was sustained by the trial court, and, relator refusing to plead further, judgment was rendered on demurrer.
¶3*122The ruling of the court in sustaining appellees’ demurrer is here assigned as error.
¶4
¶5
¶6It is not claimed that relator’s authority to prosecute this action .is found in the drainage act, but is authorized by §252 Burns 1901, §252 R. S. 1881. By this section “An executor, administrator, a trustee of an express trust, or a person expressly authorized by statute, may sue, without joining with him the person for whose benefit the action is prosecuted. A trustee of an express trust, within the meaning of this section, shall be construed to include a person with whom, or in whose name, a contract is made for the benefit of another.”
¶7Under the law it was the duty of the obligor upon entering into a contract with the auditor for the construction of the ditch to give bond with surety to the approval of such auditor, providing for a compliance with his contract. The approval of the bond rests with the auditor, and there his authority ends in that regard. The bond was given and approved as required by law. The obligation therein is one of indemnity. It is a protection to those who suffer damages and costs by reason of the contractor’s noncompliance with the contract. It is clear under the facts that the revenues of the State or county have not and will not by Karr’s failure he affected, for by the very act itself it is made the duty of the auditor to place upon the tax duplicate,' against the property assessed, all costs and expenses of the sale and resale of that part of the ditch covered by the contract. The entire additional burden is made to rest upon the landowner. He is thereby damaged. He is the party injured and interested. The bond in suit was an instrument required by the law for such improve*124ment. It is an obligation authorized by law, and from which the law, acting upon the relationship of the parties, establishes the privity and creates the liability under the bond to the parties damaged by a breach of the contract, and for all such damages such parties may be reimbursed by an action on such bond.
¶8
¶9Judgment affirmed.