¶1Appeal from an order of the Supreme Court (Platkin, J.), entered January 4, 2008 in Albany County, which, among other things, partially denied defendants’ motion for summary judgment dismissing the complaint.
¶2By a written contract, defendant Bernard Breeyear
¶3While the contract was in effect, a fire occurred in a building at the Empire State Plaza. It was later determined that the fire ignited when James Chmielewsky, a painter provided to plaintiff by defendants, improperly disposed of rags that had been soaked in a flammable solution. Plaintiff commenced this negligence and breach of contract action, seeking $594,000 in property damages against defendants. Defendants moved for summary judgment dismissing the complaint. Supreme Court partially granted the motion and dismissed the claims sounding in negligence, but denied defendants’ motion seeking dismissal of the breach of contract and indemnification claims. Defendants now appeal.
¶4Supreme Court held that, as a matter of law, Chmielewsky *1035was a special employee of plaintiff and, because he was being supervised and controlled by plaintiff at the time of the fire, no claim that required a finding that Chmielewsky was negligent could be made against defendants.
¶5Our review of the record leads us to conclude not only that Supreme Court properly denied defendants’ summary judgment motion with respect to the breach of contract and indemnification claims, but also that summary judgment should have been granted in plaintiffs favor on both of these claims. At the time of the accident, Chmielewsky—while a special employee of plaintiff—was also an employee of defendants.
¶6Similarly, Supreme Court properly denied defendants’ motion *1036seeking dismissal of plaintiffs claim that defendants, under the contract, were obligated to procure property damage liability insurance to cover plaintiff for damages to its property. The contract provided that defendants were required to obtain insurance that covered “liability of [plaintiff] with respect to all operations under this proposal and the contract” (emphasis added). As such, the contract does not limit this obligation to obtain insurance only to claims brought against plaintiff by third parties or for damages caused to plaintiffs property as the result of a third party’s negligence (see Lafarge Bldg. Materials v J. Hall, Ltd., 3 AD3d 651, 652 [2004]). As the interpretation of the parties’ agreement presents an issue which this Court can determine as a matter of law, we grant summary judgment in plaintiffs favor (see Sherba v Midstate Precast Sys., 230 AD2d 944, 946 [1996]).
¶7Cardona, PJ., Her cure, Peters and Carpinello, JJ., concur. Ordered that the order is modified, on the law, without costs, by granting summary judgment in favor of plaintiff on the first and fourth causes of action, and, as so modified, affirmed.
¶8. Following Breeyear’s death, defendant Mary Breeyear, as executor of Breeyear’s estate, continued to perform under the contract. The contract was later assigned to defendant Breeyear General Contracting Corporation.
¶9. Plaintiff does not take issue on appeal with Supreme Court’s finding that Chmielewsky was a special employee of plaintiff with the dismissal of the negligence claims.
¶10. At oral arguments, counsel for defendants conceded that a limited employer-employee relationship existed between defendants and Chmielewsky at the time of the accident.
¶11. Although plaintiff sought summary judgment in its opposition papers to defendants’ motion, it did not formally move for such relief. Nevertheless, this Court has the authority to review the record and grant summary judgment to a nonmoving party where the record, as presented, clearly establishes that the party is entitled to such relief (see CPLR 3212 [b]; Merritt Hill Vineyards v Windy Hgts. Vineyard, 61 NY2d 106,110-111 [1984]; Sherba v Midstate Precast Sys., 230 AD2d 944 [1996]).