Public-domain · open source
OpenJurist

55 Mo. App. 536

Krah v. Weidlich

Missouri Court of Appeals

Decided December 19, 1893

Missouri Court of Appeals · decided 1893-12-19

<p>Mechanics’ Liens: work on property not described in lien account. Meld, in tlie course of discussion, that a mechanics’ lien cannot be established for work, or against property, broader than the statements of the lien account and, therefore, that work done on an outhouse cannot be considered in determining the date of -the accrual of the lien account, when the lien is filed against the main building only.</p>

Affirmed · Decided 1893-12-19

Bond, J.

¶1This is an action to enforce a mechanics’ lien brought against the contractor and the owner of the building. The defense was a general denial.

¶2The lien claim sued on was sworn to on January 20, 1892. The description of the property given in the lien is: “To-wit, two-story brick building, and situated in the following described premises, to-wit.” The evidence was that appellants rendered the following bill for same work for which this suit was brought:

St. Louis, September 12, 1892.
Mr. August WeidKch to S. Krah Son, bricklayers and contractors, Debtor.
For work on house on Clark avenue, south side, between Grand avenue and Thresa avenue, Mr. Hines, as per contract.............................................. $ 659 00
August 15, by cash account............................. 319 00
Balance due.................•.................... $ 340 00

¶3There was substantial evidence adduced by respondents to the effect that appellants never did any other work on the building after the presentation of this bill. There was some evidence on the part of appellant that a small outhouse was built between the twentieth and twenty-fifth of October. In actions at *538law, appellate courts do not weigh conflicting evidence. In the case at bar, the most appellant can claim under the record is that the evidence was conflicting as to whether or not any work was done on the building specifically described in the lien claim between the twelfth of September, 1892, and the twentieth of January, 1893, a period of over four months.

¶4The trial court sitting as a jury found this controverted fact upon substantial evidence for respondent. We are, therefore, concluded by that finding. Nor do we think the work upon the out-house (privy), even if the trial court had found that it was done within four months next before the filing of the lien claim, would have entitled the appellants to a lien on the building described herein. That description is specific, and excludes any lien for improvements not embraced within its terms. According to the lien account, appellants were entitled for work done on “a two-story brick building.” This is the definite description to which appellants restricted themselves in their lien account. Appellants cannot establish a lien for work, or against property, broader than the statements of their lien claim. Revised ¡Statutes, 1889, section 6709.

¶5The result is that the judgment of the trial court herein is affirmed.

All concur.
/55/moapp/536 · .json · Public domain