Action upon a lease, by tbe terms of which the plaintiff leased to the defendants for three years certain real estate, on which there was an orchard, shrubbery, etc. The defendants bound themselves to trim and prune at the proper time each, year, and take proper care of the fruit trees, shrubbery, hedge etc. Also to gather apples and other fruits at the proper time, and deliver to 'the plaintiff two-thirds of the apples and one-half of the small fruits.

Decided 1881-06-11

Seevers, J.

¶11. practice: written instrument: demai. I. The lease was in writing and its execution was not denied under oath. It was introduced in evidence without objection, and'there was no evidence tending to show it had not been executed ° . , by tne parties. Ihe court instructed the jury that: “The plaintiff must satisfy you by a preponderance of evidence that the contract described and set out in the petition' was executed, and unless you are so satisfied your verdict will be for defendants.” As the contract was not denied under oath, and there was no evidence tending to show it had not been duly executed, its execution should have been regarded as admitted, and the jury so instructed. Instead of so doing, the question whether the contract had been executed was submitted to the jury. The action of the court in this respect was erroneous; whether it was prejudicial is not determined.

¶22. verdict : to cvkfence^ II. The plaintiff introduced evidence tending to show the defendants had in several respects failed to perform the contract on their part. The defendants gave evidence tending to show the contract was abandoned and the plaintiff took possession of the premises in the spring of 1877. The evidence also tended to show the defendants made a contract to purchase the plaintiff’s share of the apples pi’odueed in the year 1876. This statement may not be entirely correct, but it will be so conceded for the purposes of the case.

¶3The court instructed the jury if the “ loss of the plaintiff has been fully settled and paid for, or that the performance of the contract was excused by the plaintiff, or by mutual consent abandoned by the parties, or that the plaintiff waived the performance of the contract, then your verdict will be for the defendants.

¶4This instruction is erroneous in this, there was no evidence tending to show that damages caused by any of the alleged breaches was settled, or in any manner adjusted or the per*261formance thereof excused, unless it was in relation to the apples, and this we think was a debatable question.

¶5Conceding there was evidence tending to show the contract was by mutual consent abandoned, this only applied to the future, and had no tendency to show the damages caused by past breaches had been settled, or that such breaches had been excused or released.

¶6The question asked the witness Howard was, we think, improper, and therefore the objection thereto was properly sustained. No other alleged error than those considered will probably arise on the re-trial.

¶7Eeversed.