Martinez v. Villa Const. Corp.’s Empirical Analysis
1977
Citation profile
5 state decisions
How this case has been cited
Cited by 5 later decisions — most recently October 2007
5 state decisions
Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.
Relationships
Relies on Anderson v. Cold Spring Tungsten, Inc. · HOLLAND FURANCE COMPANY v. Robson · Jorgensen v. St. Paul Fire and Marine Insurance Co. · Grimes v. Barndollar · Green v. Green
Most-quoted passages
The sentences later courts lift from this opinion, ranked by how many decisions quote each — the parts of the opinion doing the work. These counts are smaller than the citation total above because most of the 5 citing decisions cite the case generally; a passage count includes only decisions quoting that exact language verbatim.
“‘“[Cjompleted operations hazard’ includes bodily injury and property damage arising out of operations or reliance upon a representation or warranty made at any time with respect thereto, but only if the bodily injury or property damage occurs after such operations have been completed or abandoned and occurs away from premises owned by or rented to the named insured. ‘Operations’ include materials, parts and equipment furnished in connection therewith. Operations shall be deemed completed at the earliest of the following times: “(1) when all operations to be performed by or on behalf of the named insured under the contract have been completed, “(2) when all operations to be performed by or on behalf of the named insured at the site of the operations have been completed, or “(3) when the portion of the work out of which the injury or damage arises has been put to its intended use by any person or organization other than another contractor or subcontractor engaged in performing operations for a principle as a part of the same project. “Operations which may require further service or maintenance work, or correction, repair or replacement because of any defect or deficiency, but which are otherwise complete, shall be deemed completed.” (Emphasis added.)”
1 later decision quote this exact passage““Operations shall be deemed completed at the earliest of the following times: (1) when all operations to be performed by or on behalf of the Named Insured under the contract have been completed, (2) when all operations to be performed by or on behalf of the Named Insured at the site of operations have been completed, or (3) when the portion of the work out of which the injury or damage arises has been put to its intended use by any person or organization other than another contractor or subcontractor engaged in performing operations for a principal as a part of the same project. “Operations which may require further service or maintenance work, or correction, repair or replacement because of any defect or deficiency, but which are otherwise complete, shall be deemed completed.””
1 later decision quote this exact passage
How this case has been treated — in progress
Whether each later court followed, distinguished, criticized, or overruled this decision. The treatment classification (task #35) runs highest-cited cases first and lights up here as it reaches this one.