Public-domain · open source
OpenJurist
← 586 FSUPP 964 - Starr Electric Co. v. Basic Construction Co.

Starr Electric Co. v. Basic Construction Co.’s Empirical Analysis

1982

Citation profile

14
cited by 14 later decisions
3
states following
July 2017
most recently cited

3 federal appellate · 4 state decisions

How this case has been cited

Cited by 14 later decisions — most recently July 2017

3 federal appellate · 4 state decisions

601982199020002010decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

Relationships

Applies 28 U.S.C. § 1291 · 9 U.S.C. § 1 (Federal Arbitration Act) · 9 U.S.C. § 4

Relies on Prima Paint Corp. v. Flood & Conklin Mfg. Co. · Mills v. Alabama · Virginia Petroleum Jobbers Association v. Federal Power Commission, Blue Ridge Gas Company, Intervenor. Petition for Review of Order of the Federal Power Commission, No. 14583. Virginia Petroleum Jobbers Association v. Federal Power Commission, Appeal From United States District Court for the District of Columbia · Washington Metropolitan Area Transit Commission v. Holiday Tours, Inc. · Schoenamsgruber v. Hamburg American Line

Most-quoted passages

The sentences later courts lift from this opinion, ranked by how many decisions quote each — the parts of the opinion doing the work. These counts are smaller than the citation total above because most of the 14 citing decisions cite the case generally; a passage count includes only decisions quoting that exact language verbatim.

  1. “George A. Fuller Company, a Maryland corporation with its principal place of business in New York, contracted as prime contractor with Richmond County Hospital Authority, Augusta, Georgia, to build a university hospital. The “General Conditions” of the prime contract included a provision that the parties would submit contract disputes to arbitration and that neither party had “a right of legal action” based on the contract until the arbitrators reached a decision. Fuller then entered into a subcontract with J. S. & H. Construction Company, a legal entity of New Mexico, under which J. S. & H. was to furnish labor and materials for the construction of the hospital. The subcontract contained no express arbitration provision, but it incorporated by-reference the “General Conditions” of the prime contract and explicitly provided that the subcontractor assumed toward the prime contractor those responsibilities and obligations which the prime contractor assumed toward the Hospital Authority in the prime contract.”
    1 later decision quote this exact passage
  2. “[a]ll claims, disputes and other matters ... arising out of, or relating to, the Contract Documents or the breach thereof”
    1 later decision quote this exact passage
  3. “assume toward the Contractor all the obligations and responsibilities which the Contractor ... assumes toward the Owner”
    1 later decision quote this exact passage

How this case has been treated — in progress

Whether each later court followed, distinguished, criticized, or overruled this decision. The treatment classification (task #35) runs highest-cited cases first and lights up here as it reaches this one.