Public-domain · open source
OpenJurist

6 Cal. 295

Cahoon v. Levy

California Supreme Court

Decided July 1, 1856

California Supreme Court · decided 1856-07-01

The following facts are admitted for the purposes of the opinion: The plaintiffs brought their action, and recovered judgment in the Court below against the defendant, Levy and others. A writ of attachment was issued at the time of bringing the action, September 15, 1853, and duly served on one Nathan, for whom Levy was erecting a house, which was not then completed.

Good law ✅— No negative treatment on recordhow we know

Decided 1856-07-01

How this case has been cited

Cited by 7 later decisions — most recently May 1909

6 state decisions

20185618601870188018901900decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

View the full empirical analysis of this case →

Mr. Chief Justice Murray delivered the opinion of the Court.

¶1Mr. Justice Terry concurred.

¶2This cause has been re-submitted to us for the purpose of obtaining our opinion upon a point, which will be decisive of the whole subject matter of the controversy.

¶3The question presented is, whether the garnishment served upon the owners of the building, before the notices by the sub-contractors, journeymen, etc., becomes a lien upon the fund in the hands of the owner, and takes precedence of the claims of sub-contractors.

¶4The statute was designed for two classes of laborers and contractors ; first, master builders, mechanics, lumber merchants, and all other persons furnishing labor or materials, by contract with the owner of the building himself; and second, sub-contractors, journeymen, etc., performing labor, or furnishing materials by contract, with the master builders or contractors, and between whom and the owner there is no privity of contract whatever. It frequently happens, that persons in building or repairing houses, wharves, etc., prefer to supervise the labor themselves, and in such eases, those engaged in the construction of, or the furnishing of materials, have, by the first section of the Act, a lien on.the building, by filing a notice thereof at any time within sixty days after its completion.

¶5The second class, those employed by the master builders, or who contract with or under the first contractors, are provided for by the second, third, and fourth sections of the Act. They look first to their employer, and next to the owner of the building, who is not responsible to them, except in case of notice served in conformity with the statute. As to the time in which notice shall be served, the law is silent. If they are to be allowed sixty days after the completion of the building to serve such notice on the owner, it will not unfrequently occur, that he will be subjected to pay the same amount twice; as it will be impossible for *297him to ascertain the claims against the principal contractor, and his agreement with him may he for payment by instalments, or on the completion of the work.

¶6We are of opinion, that the statute intended to provide an actual lien, existing from the commencement of the work until sixty days after its completion, for those enumerated in the first section; leaving all others their remedy by notice to the owner; and no time being fixed when such notice shall be given, that their lien attaches only upon the service thereof; that this mode of procedure was intended to prevent litigation, by substituting a proceeding in the nature of an attachment or garnishment ; and this class of cases is put upon the same footing as ordinary attachments in which the rule, qui prior est in tempore, potior est in jure, prevails.

¶7Judgment reversed.

/6/cal/295 · .json · Public domain