← 603 P.2d 347 - Stipe v. Theus

Stipe v. Theus’s Empirical Analysis

1979

Citation profile

17
cited by 17 later decisions
1
states following
April 2001
most recently cited

12 state decisions

How this case has been cited

Cited by 17 later decisions — most recently April 2001

12 state decisions

1201979198019902000decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

Relationships

Relies on Willbrook v. Worten · Autry v. District Court of Muskogee County · State Ex Rel. Medlin v. Ferris

Most-quoted passages

The sentences later courts lift from this opinion, ranked by how many decisions quote each — the parts of the opinion doing the work. These counts are smaller than the citation total above because most of the 17 citing decisions cite the case generally; a passage count includes only decisions quoting that exact language verbatim.

  1. ““Reviewing the provisions of § 87.1(3), it appears the Legislature, in providing the Commission shall determine the proper costs in the event of a dispute, recognized that such responsibility would be merely a continuation of the Commission’s regulatory authority in that a determination of the proper costs would be an integral part of regulating the conservation and production of oil and gas. It also appears the legislature did not intend to extend the Commission’s authority beyond that necessary to regulate the conservation and production of oil and gas because the Commission was granted only limited powers to enforce its ‘proper cost’ determination. However, we will not presume the Legislature intended to divest the district court of any of its constitutional jurisdiction when it conferred continuing jurisdiction in the Commission to determine costs in the event of a dispute arising from a forced pooling order.””
    1 later decision quote this exact passage
  2. “" * * * Such pooling order of the Commission shall make definite provisions for the payment of cost of the development and operation, which shall be limited to the actual expenditures required for such purpose not in excess of what are reasonable, including a reasonable charge for supervision. In the event of any dispute relative to such costs, the Commission shall determine the proper costs after due notice to interested parties and a hearing thereon." [Emphasis mine]”
    1 later decision quote this exact passage
  3. “Assuming arguendo that the Legislature could constitutionally confer exclusive jurisdiction in the Corporation Commission to determine the proper costs in the event of a dispute in the drilling and development of a pooled oil and gas drilling unit, § 87.1(e) may not be construed as conferring or a Legislative attempt to confer, such exclusive jurisdiction.”
    1 later decision quote this exact passage

How this case has been treated — in progress

Whether each later court followed, distinguished, criticized, or overruled this decision. The treatment classification (task #35) runs highest-cited cases first and lights up here as it reaches this one.