Savin Brothers, Inc. v. State’s Empirical Analysis
1978
Citation profile
6 federal appellate · 8 state decisions
How this case has been cited
Cited by 30 later decisions — most recently June 2003 · most notably Wolff & Munier, Inc. v. Whiting-Turner Contracting Co. (1991), Niagara Mohawk Power Corp. v. Graver Tank & Manufacturing Co. (1979)
6 federal appellate · 8 state decisions
Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.
Most-quoted passages
The sentences later courts lift from this opinion, ranked by how many decisions quote each — the parts of the opinion doing the work. These counts are smaller than the citation total above because most of the 30 citing decisions cite the case generally; a passage count includes only decisions quoting that exact language verbatim.
“`the parties are free to leave certain determinations to the judgment of the engineer and, where this has been done, the determination of the engineer is final as a matter of law, absent a showing of fraud or bad faith [citations omitted] .... the contractor is not bound by the engineer's erroneous construction of law in interpreting the contract ( Smith Contr. Co. v. City of New York, supra, [ 240 N.Y. 491 , 148 N.E. 655 (1925);] Daniels Co. v. City of New York, supra [ 196 App.Div. 856 , 188 N.Y.S. 716 (1921);] Burke v. Mayor, etc. of City of N.Y., 7 App.Div. 128 [ 40 N.Y.S. 81 (1896)])'”
1 later decision quote this exact passage · from the majority“Where one agrees to do, for a stated sum, a thing possible to be performed, he is not entitled to additional compensation merely because he encounters unforeseen difficulties.... Recovery cannot be had for extra work which actually falls within the [sub]contract or the plans and specifications ... but recovery may be had for work outside the contract where the [sub]contractor was in fact specifically ordered to do work not within the scope of that called for by the [sub]contract.”
1 later decision quote this exact passage · from the majority“something necessarily required in the performance of the contract which arises from conditions which could not be anticipated.”
1 later decision quote this exact passage · from the majority
How this case has been treated — in progress
Whether each later court followed, distinguished, criticized, or overruled this decision. The treatment classification (task #35) runs highest-cited cases first and lights up here as it reaches this one.