South Dakota Public Utilities Commission v. Federal Energy Regulatory Commission’s Empirical Analysis

690 F.2d 674 · 1982

Citation profile

11
cited by 11 later decisions
2
states following
September 1987
most recently cited

5 federal appellate · 3 state decisions

Relationships

Applies 42 U.S.C. § 2021

Relies on Montana-Dakota Utilities Co. v. Northwestern Public Service Co. · Arkansas Louisiana Gas Co. v. Hall · New England Power Company v. New Hampshire Massachusetts · Union Electric Co. v. Federal Energy Regulatory Commission

Most-quoted passages

The sentences later courts lift from this opinion, ranked by how many decisions quote each — the parts of the opinion doing the work. These counts are smaller than the citation total above because most of the 11 citing decisions cite the case generally; a passage count includes only decisions quoting that exact language verbatim.

  1. “The Amendment to the Coordinating Agreement of Northern States Power Company (Minnesota) and Northern Power Company (Wisconsin) filed with the Commission ... is just and reasonable. It is approved as a rate schedule change pursuant to § 205 of the Federal Power Act subject to the modification ordered in Paragraph (B) below.”
    2 later decisions quote this exact passage · from the majority
  2. “Commission's denial turned on lack of need for the nuclear plant, economic disbenefits, and superiority of alternative means of generation.”
    1 later decision quote this exact passage · from the majority

How this case has been treated — in progress