Maynard v. Lange

Oregon Supreme Court

Decided July 21, 1914

Oregon Supreme Court · decided 1914-07-21

<p>Mechanics’ Liens—Waiver—Effect of Contractors’ Bond.</p> <p>1. A contractors’ bond, to indemnify the owner against any lien or claim for which the owner might become liable and whieh is chargeable to the contractors, to pay all indebtedness incurred by the contractors in carrying out the contract, and to complete the contract free from mechanics’ liens, does not operate as a waiver of lien of the contractors themselves.</p> <p>[As to stipulation in building contract against mechanics’ liens as precluding contractor from filing lien, see note in Ann. Cas. 1913E, 562.]</p> <p>Mechanics’ Liens—Right to Lien—Performance on Contract.</p> <p>2. Under Sections 725, 726, L. O. L., providing that the evidence shall correspond with the substance of the material allegations and each party shall prove his own affirmative allegations, where the contract alleged in a suit to foreclose a contractors’ lien provided for drainage from exterior moisture and seepage, which was omitted, and for an even and sufficient drainage to all floor drains and traps, while the floor as fashioned would not completely drain to the outlets, the lien will not be enforced, but the contractors will be remitted to their remedy at law.</p>

Relies on Winder v. Caldwell · Boyd v. Jacobs · Hannan v. Greenfield

Good law ✅— No negative treatment on recordhow we know

Affirmed · Decided 1914-07-21

How this case has been cited

Cited by 8 later decisions — most recently November 1948

8 state decisions

401914192019301940decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

View the full empirical analysis of this case →

Mr. Justice Burnett

¶1delivered the opinion of the court.

¶21. The first question for consideration is the effect to be given to the bond in question. We remember that the lien is claimed in favor of the contractors themselves, and not for any mechanic, materialman, laborer, or other person, besides contractors, mentioned in the statute. There are three stipulations in the bond: (1) That the contractors “shall indemnify and save harmless the owner from and against all or any lien or claim for which, if established, the owner 'of the said premises might become liable, and which is *563chargeable to the contractors”; (2) “and if they shall duly and promptly pay and discharge all indebtedness that may be incurred by the contractors in carrying out the said contract”; (3) “and complete the same free from mechanics’ liens.” No question is made about violation of the first two stipulations mentioned. The defendant rests his case on the condition that the contractors should complete the work free from mechanics’ liens. In Gray v. Jones, 47 Or. 40 (81 Pac. 813), the stipulation of the contract for building was, among other things, as follows:

¶3“The party of the first part will save the party of the second part free and harmless from the payment of any and all liens which may be enforced on account of any material furnished or labor performed on said building and premises, or any part of either thereof; and the said party of the second part further covenants and agrees that he will not allow any laborer’s, mechanic’s, materialman’s or any lien or liens to be filed against the said building and premises, or any part of either thereof, and, further, that the said building and premises and every part of either thereof shall be at all times free from any and all liens.”

¶4This stipulation was against “any and all liens,” without discrimination between the claim of the original contractor and that of any subcontractor, mechanic or laborer, and it was properly held that this constituted a waiver on the part of the contractor of any lien in his own favor. Having promised to keep the building and premises always free from “any and all liens” without distinction, he could not be heard to claim a lien for himself.

¶5The statute, however, differentiates between the original contractor, mechanic, artisan, materialman and laborer. It is a duty of the former to file his claim of lien in 60 days, and of all other parties to file their *564claim within 30 days, after the completion of the work. The contractor is not in the same classification with other persons named in the statute. The distinction between the original contractor and a mechanic is pointed out in the following authorities: Savannah etc. R. Co. v. Callahan, 49 Ga. 506; Winder v. Caldwell, 55 U. S. 434 (14 L. Ed. 487); New Orleans v. Pohlmann, 45 La. Ann. 219 (12 South. 116); Theobalds v. Conner, 42 La. Ann. 787 (7 South. 689); Krakauer v. Locke, 6 Tex. Civ. App. 446 (25 S. W. 700); Parks v. Locke (Tex. Civ. App.), 25 S. W. 702. .In the light of these precedents, we hold that the bond mentioned did not stipulate against the claim of lien in favor of the contractors themselves, and hence cannot operate against them as a waiver.

¶62. We are therefore remitted to the duty of trying the case de novo on the testimony reported in the record. The principal issue in the case is upon the allegation of plaintiffs that they duly performed the contract as modified by the changes made from time to time as the work progressed which averment is traversed by the answer. The defendant charges, among other things, that:

¶7“The plaintiffs neglected and failed to provide any drainage from exterior moisture and seepage, with soil drains under the walls, or to place therein any drains whatever.”

¶8This is explicitly provided for in the specifications made part of the contract, and the plaintiffs themselves admit that it was overlooked and not installed. It is also required that the contractors shall “lay a cement floor over entire basement area, … with an even and sufficient drainage to all floor drains and traps.” The testimony of the plaintiffs shows that the basement floor is so fashioned that it will not com*565pletely drain to the outlets. Other defects noted are clearly disclosed by the testimony before us, but these are sufficient for illustration. The specifications further provide:

¶9“The contractor shall make no changes, alterations or substitutions to these specifications, or to the blueprints and drawings, nor to the building during its construction without permission of the architect in writing, approved of by the owner in writing, and duly acknowledged by the contractor in writing over his own signature.”

¶10No pretense is made that the omission of the drain tile, or the manner in which the basement floor was constructed, was authorized by the architect or the owner. Having alleged performance of the contract, and it having been denied by the defendant, it was incumbent upon the plaintiffs to prove the allegation as laid, under the statutes that “ evidence shall correspond with the substance of the material allegations” and “each party shall prove his own affirmative allegations”: Sections 725 and 726, L. O. L.; Hannan v. Greenfield, 36 Or. 97 (58 Pac. 888); Young v. Stickney, 46 Or. 101 (79 Pac. 345); Richardson v. Investment Co., 66 Or. 353 (133 Pac. 773).

¶11The conclusion is that the plaintiffs cannot prevail in this suit to foreclose their lien, but must be remitted to such action at law, either on the contract or upon the quantum meruit, as they may think proper in the premises.

¶12The decree of the Circuit Court is affirmed.

¶13Affirmed.

Mr. Chief Justice McBride, Mr. Justice Bean and Mr. Justice Eakin concur.