Cited by 55 later decisions — most recently September 2017 · most notably Penland v. BIRD COAL COMPANY (1957), Godley v. County of Pitt (1982)

53 state decisions

1601952196019701980199020002010decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

Relationships

Relies on Hayes v. . Elon College · Town of Burnsville v. Boone · Rader v. Queen City Coach Co. · Beach v. . McLean · Fox v. Cramerton Mills, Inc.

Most-quoted passages

The sentences later courts lift from this opinion, ranked by how many decisions quote each — the parts of the opinion doing the work. These counts are smaller than the citation total above because most of the 55 citing decisions cite the case generally; a passage count includes only decisions quoting that exact language verbatim.

  1. “Any principal contractor, intermediate contractor, or subcontractor who shall sublet any contract for the performance of any work without requiring from such subcontractor or obtaining from the Industrial Commission a certificate, issued by the Industrial Commission, stating that such subcontractor has complied with G.S. 97-93 hereof, shall be liable, irrespective of whether such subcontractor has regularly in service less than four employees in the same business within this State, to the same extent as such subcontractor would be if he were subject to the provisions of this Article for the payment of compensation and other benefits under this Article on account of the injury or death of any such subcontractor, any principal or partner of such subcontractor or any employee of such subcontractor due to an accident arising out of and in the course of the performance of the work covered by such subcontract. If the principal contractor, intermediate contractor or subcontractor shall obtain such certificate at the time of subletting such contract to subcontractor, he shall not thereafter be held liable to any such subcontractor, any principal or partner of such subcontractor, or any employee of such subcontractor for compensation or other benefits under this Article. If the subcontractor has no employees and waives in writing his right to coverage under this section, the principal contractor, intermediate contractor, or subcontractor subletting the contract shall not thereafter be”
    4 later decisions quote this exact passage
  2. “[T]here is [no evidence] that Halsey Hardwood at any time sublet any part of its logging operations or other work to Spivey, nor made any contract with him for the performance of work of any kind. All the evidence tends to show . . . that Spivey was cutting timber which he owned absolutely. . . . Halsey Hardwood had no contractual rights of any kind in the stumpage. Spivey owned his own logging equipment, conducted his own logging operations and sold his logs in the open market. The firms to whom he sold the logs had no control or right of control over his mode of logging operations or disposal of logs. On this record Spivey at no time stood in the position of subcontractor to Halsey Hardwood . . ., nor was Halsey Hardwood ever at any time liable, under G.S. 97-19 . . ., for any injuries that may have been sustained by Spivey's employees. . . . . [N.C.G.S. § 97-19] does not apply to an independent employer who, as in the case of Spivey, produces or gets out raw materials of his own, like logs, and sells them in the open market to a processor-purchaser like Halsey Hardwood who has no control whatsoever over the operations of the independent employer.”
    1 later decision quote this exact passage
  3. “Any principal contractor, intermediate contractor, or subcontractor who shall sublet any contract ... without requiring from such subcontractor or obtaining from the Industrial Commission a certificate, ... stating that such subcontractor has complied with G.S. 97-93 hereof, shall be liable,... to the same extent as such subcontractor would be ... for the payment of compensation and other benefits under this Article.... If the principal contractor ... shall obtain such certificate at the time of subletting such contract ... he [is not] liable ... for compensation....”
    1 later decision quote this exact passage

How this case has been treated — in progress