Public-domain · open source
OpenJurist

76 Ill. App. 372

Rawle v. Gilmore

Appellate Court of Illinois

Decided May 9, 1898

Appellate Court of Illinois · decided 1898-05-09

Assuntpit, for a balance due on a contract. Trial in the Superior Court of Cook County; the Hon. Jonas Hutchinson, Judge, presiding. Verdict and judgment for defendant. Appeal by pi an tiff.

Relies on Gilmore v. Courtney · Arnold v. Bournique · Snell v. Brown

Good law ✅— No negative treatment on recordhow we know

Reversed and remanded · Decided 1898-05-09

How this case has been cited

Cited by 6 later decisions — most recently April 2014

6 state decisions

201898190019101920193019401950196019701980199020002010decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

View the full empirical analysis of this case →

Mr. Justice Sears

¶1delivered the opinion of the court.

¶2It was contended by appellee in the trial court, as here, that the suit of appellant could not be maintained because:

¶31st. He had failed to obtain a certificate of the architect, a condition precedent to right of payment, as provided by the contract, and had not sufficiently excused such failure.

¶4. 2d. He had not complied with the provisions of section 35 of the mechanic’s lien act.

¶5The trial court, acting upon one of these grounds, and it would seem from the bill of exceptions to have been the second, held that appellant could not recover.

¶6We have, then, to determine whether the jury would have been warranted by the evidence in a finding that the facts excused appellant from obtaining the architect’s certificate, as a condition precedent to payment, and also warranted in a finding that there had been a waiver of the right to demand a statement under oath, as provided by the statute.

¶7There was evidence from which the jury might have found that the work specified in the contract was completed within the time fixed by the contract, and that there was no valid ground or reason for the refusal of the architect to give a certificate for the balance due. In such case it is for the jury to determine whether the refusal of the architect to issue his certificate is so far fraudulent, i. e., ungrounded and capricious, as to be no bar to the contractor’s right to payment. Badger v. Kerber, 61 Ill. 328; County of Cook v. Harmes, 108 Id. 151; Michaelis v. Wolf, 136 Id. 68; Arnold v. Bournique, 144 Ill. 132.

¶8The mere refusal to issue the certificate upon grounds which were known to be fictitious and without foundation, might be found to constitute a fraudulent refusal. Snell v. Brown, 71 Ill. 133; Foster v. Charles, 7 Bingh. 104.

¶9It has been held in a number of cases, that a failure to comply with the statute requiring a statement under oath of the number and names of sub-contractors, mechanics or workmen, etc., with amounts due them, etc., as provided by section 35 of the mechanic’s lien act of 1887, will bar a right to recover in assumpsit for labor or material, as well as right to enforce a lien. Gilman v. Courtney, 158 Ill. 437; Floyd v. Rathlege, 41 Ill. App. 370; Bonheim v. Meaney, 43 Id. 532.

¶10But it is also held that the owner’s right to such statement may be waived so as to permit recovery in action at law without the furnishing of the statement. Floyd v. Rathlege, supra; Burnside v. O’Hara, 35 Ill. App. 150; Morse v. Crate, 43 Id. 514.

¶11If there is evidence here tending to show such a waiver, and from which a jury would be warranted in finding that there was in fact a waiver, then the issue should have been left to the jury for determination.

¶12Two facts appear in the evidence which bear upon this issue, viz.: the former certificate issued by the architect without having in fact obtained any statement under oath by the contractor; and the tender of a certificate for $1,200 without requiring such statement. The jury might have found from the evidence that the former certificate was issued after all work had been completed under the contract. No liabilities for labor or material could then have been afterward incurred by the contractor for the work done under the contract. By its recitals the certificate admits a furnishing of the required statement at that time, although none was in fact made. This we think might support a finding by the jury that the statement had been thereby waived. The tender of the certificate for $1,200 might be held, as a matter of fact, to have constituted • a waiver to any statement, at least as to a right to payment of the $1,200. Nor do we think the contention tenable that by refusal of the tender the waiver, was necessarily thereby withdrawn.

¶13The effect of each of these items of evidence presented a question for the determination of the jury, and should have been submitted to them. The judgment is therefore reversed and the cause remanded.

/76/illapp/372 · .json · Public domain