76 N.H. 572

79 A 690

Thyng v. Hussey

Supreme Court of New Hampshire

Decided April 4, 1911

Supreme Court of New Hampshire · decided 1911-04-04

Assumpsit. The two actions were tried together by Stóne, J., who found a verdict for Thyng in his suit for $615.34 and for Hussey in his suit for $410.13, and ordered execution to issue for $205.21, the balance due Thyng. In the first suit there was a plea of the statute of limitations as to items amounting to $269.20 not accruing within six years of the date of the writ.

Relies on Batchelder v. Manchester Street Railway · Rossiter v. Colby

Decided 1911-04-04

Peaslee, J.

¶1 The case is not distinguishable from Bossiter v. Colby, 71 N. H. 386. The promise was a conditional one, and Thyng does not bring himself within its terms. His claim that the question has not been properly raised because there was no motion to set the verdict aside as against the evidence cannot be sustained. The presiding justice had ruled, subject to exception, that the evidence showed a new promise. That ruling was the law of the trial, and if it was correct the verdict was properly found. The question of the soundness of the ruling was properly saved (P. S., c. 204, ss. 11, 12), and this was all that was necessary to preserve the rights of the parties. Batchelder v. Railway, 72 N. H. 329.

¶2 The judgment for Thyng should be reduced to $346.14, and execution awarded to Hussey for the balance due him of $63.99, with interest from the date of the writ.

¶3 Exception sustained.

¶4 All concurred.