79 A.D.3d 588

Asensio v. Casa 74th Development, LLC

Appellate Division of the Supreme Court of the State of New York · decided 2010-12-21

Cited by 4 later decisions — most recently March 2012

Key passage — most relied on by later courts

“In that case, as here, the offering plan provided: [I]f Purchaser finds that Sponsor’s improvements as described in the Plan or in the ... Agreement ... have not been fully completed, although such improvements have been substantially completed, then Sponsor ... and Purchaser will at the time of such execution agree upon and set forth in the Inspection Statement a list of the incomplete work to be completed by Sponsor following the Closing.”

quoted by 1 later decision, including Waverly Properties, LLC v. KMG WAVERLY, LLC

Good law ✅— No negative treatment on recordhow we know

Decided 2010-12-21

View the full empirical analysis of this case →

Nardelli and Freedman, JJ.

¶1dissent in part in a memorandum

¶2by Nardelli, J., as follows: Since I believe that plaintiff terminated the contract when he wrote a letter to the sponsor’s attorney demanding the return of his purchase money deposit, and advising “that a material amount of construction work remains completely undone,” I would affirm the order in its entirety, and thus leave the court’s decision to strike the notice of pendency undisturbed.

¶3In May 2007, defendant Casa 74th Development, LLC, as sponsor, filed an offering plan for a proposed condominium at 255 East 74th Street, in Manhattan. In pertinent part, in a section entitled “Rights and Obligations of Sponsor,” the plan provided: “[I]f Purchaser finds that Sponsor’s improvements as *590described in the Plan or in the Option Agreement or other writing duly executed and delivered by Sponsor, have not been fully completed, although such improvements have been substantially completed, then Sponsor or its designated representative and Purchaser will at the time of such execution agree upon and set forth in the Inspection Statement a list of the incomplete work to be completed by Sponsor following the Closing without provision for escrow. Sponsor’s obligation thereunder shall survive delivery of the deed to the Purchaser. The failure of Sponsor to complete such work shall not be grounds for Purchaser to delay the Closing or to unilaterally refuse to pay the full Balance of the Purchase Price at Closing.”

¶4In July 2007, the sponsor and plaintiff executed an option agreement for the sale of Unit 24C. The agreement expressly incorporated the offering plan by reference, and recited that the plan’s provisions would govern in the event of any inconsistencies between the two. The agreement also provided: “[I]f all other prerequisites not involving the construction of the Unit are met, Purchaser shall be obligated to close and complete payment of the full Purchase Price (without any credit against or abatement in the Purchase Price and without provision for escrow) once a Temporary or Permanent Certificate of Occupancy is issued for the Unit (notwithstanding any construction items noted on Purchaser’s Inspection Statement (as hereinafter defined) remaining for Sponsor to complete and/or correct in accordance with its obligations under the Plan, and notwithstanding the incomplete construction and/or decoration of any other portions of the Building not affecting the Unit).”

¶5The agreement further provided that in the event that plaintiff did not attend and pay the purchase price at a scheduled closing, then the agreement would be “deemed cancelled.” In such case, the sponsor would be entitled to retain all of the down payment monies and would be entitled to sell the unit to another purchaser. The agreement also gave the sponsor the right to cancel the agreement if the purchaser failed to perform other obligations, including payment of the purchase price when due.

¶6Closing was initially set for January 2009, and was rescheduled several times. On March 31, 2009, the sponsor gave notice that closing had been rescheduled to April 15, 2009.

¶7On April 8 and 14, 2009, plaintiff’s architect inspected the premises, as provided for in the agreement. The architect reported some 104 construction defects and incomplete items. Plaintiff took the position that the construction of the unit was substantially incomplete, and refused to close on the unit.

¶8*591On April 16, 2009, the sponsor declared plaintiff to be in default, and advised him that unless he cured the default by closing on the unit on or before May 20, 2009, the agreement would be cancelled and the sponsor would retain the deposit monies as liquidated damages.

¶9On May 8, 2009, plaintiff wrote the sponsor a letter demanding the return of the $897,000 in deposit monies, asserting “that a material amount of construction work remains completely undone.” A week later, on May 15, 2009, plaintiff filed an application with the Attorney General’s Real Estate Finance Bureau for a “Determination on the Disposition of Downpayments.” Plaintiff asserted that the agreement was “unenforceable” and “void given the Sponsor’s refusal to address any one of the construction issues raised by the Applicant.” As an alternative to rescission of the agreement, plaintiff requested that if the agreement were found to be enforceable, he be given a “reasonable opportunity to close” on the sale.

¶10Thus, as of May 8, 2009, two possibilities were presented. The first is that the condominium was substantially complete in accordance with the provisions of the contract, and, therefore, plaintiff was obligated to close upon demand by the sponsor. The second is that the condominium was not substantially complete and plaintiff was within his rights to refuse to close, and demand a return of his down payment. Which of the alternatives is correct is an issue that remains to be decided.

¶11In the interim, however, plaintiff is not entitled to maintain a lis pendens on the property, and hold the condominium hostage during the course of the litigation. Inasmuch as he, on two different occasions, evinced an intention to terminate the contract, his sole recourse is to get his money back, if, indeed, the sponsor failed to comply with its obligations under the contract.

¶12The majority finds that plaintiff never definitely opted for rescission of the contract, and, thus, had not made an election of remedies, citing 331 E. 14th St. v 331 E. Corp. (293 AD2d 361 [2002], Iv dismissed 98 NY2d 727 [2002]). Yet, in that case, this Court made clear that an election of remedies will be found to have been made if “ ‘a party must have chosen one of two or more co-existing inconsistent remedies, and in reliance upon that election, that party must have also gained an advantage, or the opposing party must have suffered some detriment’ ” (id. at 361, quoting Prudential Oil Corp. v Phillips Petroleum Co., 418 F Supp 254, 257 [SD NY 1975], citing, inter alia, Hill v McKinley, 254 App Div 283 [1938]).

¶13I believe that plaintiff had elected the remedy of rescission with his May 8th notice of cancellation, and confirmed it in his *592May 15th submission to the Attorney General. It is evident that plaintiff has now gained an advantage, and the sponsor has suffered a detriment. Plaintiff advised on May 8th that he was refusing to close, and demanded a return of his down payment. He did not file a notice of pendency until January .8, 2010, eight months later, when he also filed a complaint in which he sought, alternatively, specific performance or damages. In the interim, however, the sponsor had obtained another buyer. Plaintiff himself sent an e-mail to the prospective buyer’s attorney two days after the action was instituted, in which he advised that he had filed a lis pendens. The e-mail stated, in pertinent part, “I understand from you that your proposed buyer has agreed to a price and accepted a contract that he has or is prepared to execute.”

¶14It is therefore evident that plaintiff recognized that the sponsor was prepared to sell the unit to another buyer, and that he consequently had lost significant economic leverage with the sponsor in his dispute over the condition of the unit. By pressuring the prospective plaintiff to withdraw, and now seeking specific performance, plaintiff sought to gain an improper advantage, and the sponsor suffered a detriment.

¶15Such circumstances justify a finding that the portion of the action seeking specific performance was commenced not in good faith, but as a Damoclean sword to force the sponsor into incurring the cost of carrying the unit while the dispute over whether plaintiff is entitled to a refund is litigated (see Israelson v Bradley, 308 NY 511, 516 [1955]). Vacatur of the notice of pendency pursuant to CPLR 6514 (b) was thus appropriate, and the order should be affirmed.