United States v. Boeing Co.’s Empirical Analysis
845 F.2d 476 · 1988
Citation profile
3 federal appellate · 2 district ·
How this case has been cited
Cited by 15 later decisions (1 by the Supreme Court) — most recently November 2010
3 federal appellate · 2 district ·
Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.
Appellate journey
Relationships
Applies 18 U.S.C. § 1914 · 18 U.S.C. § 209 · 28 U.S.C. § 2415 (Indian Claims Limitation Act of 1982) · 28 U.S.C. § 2416
Relies on United States v. Mississippi Valley Generating Co. · Kenealy v. United States · Jankowitz v. United States · Continental Management, Inc. v. United States · Jankowitz v. United States
Most-quoted passages
The sentences later courts lift from this opinion, ranked by how many decisions quote each — the parts of the opinion doing the work. These counts are smaller than the citation total above because most of the 15 citing decisions cite the case generally; a passage count includes only decisions quoting that exact language verbatim.
“facts material to the right of action are not known and reasonably could not be known by an official of the United States charged with the responsibility to act in the circumstances. ...”
3 later decisions quote this exact passage · from the concurrence“[E]very action for money damages brought by the United States ... which is founded upon any contract express or implied in law or fact, shall be barred unless the complaint is filed within six years after the right of action accrues ....”
2 later decisions quote this exact passage · from the concurrence“That official, according to the Justice Department, was the DOD contracting officer for Boeing who learned the relevant facts in a memo from the DCAA on March 26, 1982. The government fails to explain, however, why DCAA employees charged with auditing responsibilities were not charged with responsibility to act here. Conclusory statements that the contracting officer was the first official with the knowledge and ability to recognize a conflict do not justify tolling the statute under § 2416(c) and are refuted by the fact that DCAA employees and managers recognized that a problem existed. The decision to refer that problem to the contracting officer does not diminish their ability to act.”
1 later decision quote this exact passage · from the majority
How this case has been treated — in progress
Whether each later court followed, distinguished, criticized, or overruled this decision. The treatment classification (task #35) runs highest-cited cases first and lights up here as it reaches this one.