Public-domain · open source
OpenJurist
← 86 ILL 78 - Finney v. Condon

Finney v. Condon’s Empirical Analysis

1877

Citation profile

26
cited by 26 later decisions
1
cited 1 times by the Supreme Court
8
states following
March 2000
most recently cited

2 federal appellate · 1 district · 17 state decisions

How this case has been cited

Cited by 26 later decisions (1 by the Supreme Court) — most recently March 2000 · most notably Pearlman v. Reliance Insurance (1962), Prairie State Nat Bank of Chicago v. United States (1896)

2 federal appellate · 1 district · 17 state decisions

6018771880189019001910192019301940195019601970198019902000decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

Relationships

Relies on Ryan v. Trustees of Shawneetown · McAvoy v. Long

Most-quoted passages

The sentences later courts lift from this opinion, ranked by how many decisions quote each — the parts of the opinion doing the work. These counts are smaller than the citation total above because most of the 26 citing decisions cite the case generally; a passage count includes only decisions quoting that exact language verbatim.

  1. ““The law upon this subject seems to be, the reserved per cent to be withheld until the completion of the work to be done is as much for the indemnity of him who may be a guarantor of the performance of the contract, as for him for whom it is to be performed. And there is great justness in the rule adopted. Equitably, therefore, the sureties in such cases are entitled to have the sum agreed upon held as a fund out of which they may be indemnified, and if the principal releases it without their consent it discharges them from their undertaking. The principle is, the withdrawal of the fund agreed upon as security for the performance of the contract without his consent is a prejudice to the surety or guarantor. Sureties and guarantors are not to be made liable beyond the express terms of their engagements. They have the right to prescribe the terms and conditions on which they will assume responsibility, and neither of the principals can change those terms without the consent of the sureties, even with a view to avoid ultimate liability.””
    2 later decisions quote this exact passage · from the majority
  2. ““When a contractor had undertaken to perform certain work, and it was agreed that three-fourths of the work, as finished, should be paid for every two months, and the remaining one-fourth, upon the completion of the whole work, it was held that the sureties for the due performance of the contract were released from their liability, by reason of payments exceeding three-fóurths of the work done, having been made to the contractor, without the consent of the sureties before the completion of the whole work.””
    1 later decision quote this exact passage · from the majority

How this case has been treated — in progress

Whether each later court followed, distinguished, criticized, or overruled this decision. The treatment classification (task #35) runs highest-cited cases first and lights up here as it reaches this one.