Weeks v. . Little’s Empirical Analysis
1882
Citation profile
2 federal appellate · 1 district · 20 state decisions
How this case has been cited
Cited by 25 later decisions — most recently January 1931 · most notably Mosler Safe Co. v. Maiden Lane Safe Deposit Co. (1910), Jefferson Hotel Co. v. Brumbaugh (1909)
2 federal appellate · 1 district · 20 state decisions
Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.
Relationships
Relies on Stewart Howell v. . Keteltas
Most-quoted passages
The sentences later courts lift from this opinion, ranked by how many decisions quote each — the parts of the opinion doing the work. These counts are smaller than the citation total above because most of the 25 citing decisions cite the case generally; a passage count includes only decisions quoting that exact language verbatim.
“‘‘it is true he (the referee) also finds that some work was delayed which was not affected by the delay of the defendant. We do not see how that fact alters the just result. To effect that would require us to assume what is not proved, and we cannot know that there would have been delay in the independent work if the dependent work had not'been hindered. The contractor could gain nothing by haste and pressure in one direction so long as entire completion was delayed by his employers. We cannot divide and apportion the fault. It Is enough that damages were payable upon a failure of entire completion, and that was rendered impossible by the defendant’s act, and her executor cannot recover for a failure which she made inevitable. But for that we cannot say that there would have been any delay beyond the contract time.””
1 later decision quote this exact passage“"The rule is well settled that, where the work to be performed by the builder cannot be performed until the other work provided to be done by the owner or his employes is finished, the failure by the latter to complete their work in season to enable the builder to end his within the time limited by the contract is a sufficient excuse for his delay beyond the agreed period of completion.””
1 later decision quote this exact passage
How this case has been treated — in progress
Whether each later court followed, distinguished, criticized, or overruled this decision. The treatment classification (task #35) runs highest-cited cases first and lights up here as it reaches this one.