Public-domain · open source
OpenJurist
← 909 SO2D 58 - Hill Bros. Const. & Engineering Co. v. Mtc

Hill Bros. Const. & Engineering Co. v. Mtc’s Empirical Analysis

2005

Citation profile

8
cited by 8 later decisions
1
states following
September 2020
most recently cited

6 state decisions

How this case has been cited

Cited by 8 later decisions — most recently September 2020

6 state decisions

40200520102020decided

Later decisions citing this case, by decade. The current decade is in progress, and our corpus holds fewer opinions from the most recent years, so the latest bars are undercounted — not a real decline.

Relationships

Relies on Immigration & Naturalization Service v. Yueh-Shaio Yang · 656 So. 2d 790 - Palmer v. Anderson Infirmary Benevolent Ass'n · 774 So. 2d 421 - PERC v. Marquez · 604 So. 2d 312 - McGowan v. Miss. State Oil & Gas Bd. · 672 So. 2d 1196 - Board of Law Enforcement Officers Standards and Training v. Butler

Most-quoted passages

The sentences later courts lift from this opinion, ranked by how many decisions quote each — the parts of the opinion doing the work. These counts are smaller than the citation total above because most of the 8 citing decisions cite the case generally; a passage count includes only decisions quoting that exact language verbatim.

  1. “"Arbitrary" means fixed or done capriciously or at pleasure. An act is arbitrary when it is done without adequately determining principle; not done according to reason or judgment, but depending upon the will alone, -absolute in power, tyrannical, despotic, non-rational, -implying either a lack of understanding of or a disregard for the fundamental nature of things. "Capricious" means freakish, fickle, or arbitrary. An act is capricious when it is done without reason, in a whimsical manner, implying either a lack of understanding of or a disregard for the surrounding facts and settled controlling principles....”
    2 later decisions quote this exact passage
  2. “The irregularity did not alter the bidding process, did not provide any bidder with an advantage or benefit over any other bidder, did not prejudice the rights of any other bidder or the public, did not alter the price, quality!,] or quantity of its bid, and the waiver of the irregularity did not provide an opportunity for fraud or favoritism or affect the integrity of the competitive bidding process. Therefore, the MTC retained the authority to waive the irregularity and award the bid to Iafrate. The minutes of the MTC constitute relevant and substantial evidence that the MTC considered this matter seriously, made the appropriate findings on record, and acted within its discretion in awarding the project to Iafrate. The trial court correctly noted that to have awarded the contract to Hill Brothers would have done a disservice to taxpayers of this State and would have also been contrary to the very purpose of competitive bidding.”
    1 later decision quote this exact passage
  3. “is to determine whether the judgment (1) was supported by substantial evidence; or (2) was arbitrary or capricious; or (3) was beyond the power of the lower authority to make; or (4) violated some statutory or constitutional right of the complaining party.”
    1 later decision quote this exact passage · from the dissent

How this case has been treated — in progress