← 994 F.2d 783 - Wilner v. United States

Wilner v. United States’s Empirical Analysis

994 F.2d 783 · 1993

Citation profile

6
cited by 6 later decisions
April 2005
most recently cited

Relationships

Applies 41 U.S.C. § 605 · 41 U.S.C. § 609

Relies on South Corporation v. United States · Caci, Inc.-Federal v. United States · J. D. Hedin Construction Co. v. United States · 69 F. Supp. 409 - George A. Fuller Co. v. United States · Paragon Energy Corp. v. United States

Most-quoted passages

The sentences later courts lift from this opinion, ranked by how many decisions quote each — the parts of the opinion doing the work. These counts are smaller than the citation total above because most of the 6 citing decisions cite the case generally; a passage count includes only decisions quoting that exact language verbatim.

  1. “The reason that the determination of the critical path is crucial to the calculation of delay damages is that only construction work on the critical path had an impact upon the time in which the project was completed.” G.M. Shupe, Inc. v. United States, 5 Cl.Ct. 662 , 728 (1984), cited with approval in Kelso v. Kirk Bros. Mechanical Contractors, Inc., 16 F.3d 1173 , 1177 (Fed.Cir.1994). Regarding the duct revision work, the Claims Court stated: "Without a critical path analysis, the court cannot exclude the possibility that the contractor caused concurrent delay on the project.” Wilner, 26 Cl.Ct. at 274 . As for the OWJ revision work, the court stated: “The absence of a critical path analysis prevents the court from discerning whether the OWJ design defect may have been discovered earlier, but for a delay of the contractor.... The evidence relating to the OWJ revision work is insufficient for this court to attribute critical path delay to the Navy.”
    1 later decision quote this exact passage · from the majority
  2. “Where both parties to a contract contribute to delay, neither can recover damages, unless there is in the proof a clear apportionment of the delay and the expense attributable to each party.”
    1 later decision quote this exact passage · from the majority

How this case has been treated — in progress

Whether each later court followed, distinguished, criticized, or overruled this decision. The treatment classification (task #35) runs highest-cited cases first and lights up here as it reaches this one.