TITLE 42 - US CODE - SUBCHAPTER VI - LICENSING AND REGULATION OF URANIUM ENRICHMENT FACILITIES

42 USC 2297f - Gaseous diffusion facilities

(a) Issuance of standards 
Within 2 years after October 24, 1992, the Nuclear Regulatory Commission shall establish by regulation such standards as are necessary to govern the gaseous diffusion uranium enrichment facilities of the Department in order to protect the public health and safety from radiological hazard and provide for the common defense and security. Regulations promulgated pursuant to this subsection shall, among other things, require that adequate safeguards (within the meaning of section 2167 of this title) are in place.
(b) Annual report 

(1) In general 
Not later than the date on which a certificate of compliance is issued under subsection (c) of this section, the Nuclear Regulatory Commission, in consultation with the Department and the Environmental Protection Agency, shall report to the Congress on the status of health, safety, and environmental conditions at the gaseous diffusion uranium enrichment facilities of the Department.
(2) Required determination 
Such report shall include a determination regarding whether the gaseous diffusion uranium enrichment facilities of the Department are in compliance with the standards established under subsection (a) of this section and all applicable laws.
(c) Certification process 

(1) Establishment 
The Nuclear Regulatory Commission shall establish a certification process to ensure that the Corporation complies with standards established under subsection (a) of this section.
(2) Periodic application for certificate of compliance 
The Corporation shall apply to the Nuclear Regulatory Commission for a certificate of compliance under paragraph (1) periodically, as determined by the Commission, but not less than every 5 years. The Commission shall review any such application and any determination made under subsection (b)(2) of this section shall be based on the results of any such review.
(3) Treatment of certificate of compliance 
The requirement for a certificate of compliance under paragraph (1) shall be in lieu of any requirement for a license for any gaseous diffusion facility of the Department leased by the Corporation.
(4) NRC review 

(A) In general 
The Nuclear Regulatory Commission, in consultation with the Environmental Protection Agency, shall review the operations of the Corporation with respect to any gaseous diffusion uranium enrichment facilities of the Department leased by the Corporation to ensure that public health and safety are adequately protected.
(B) Access to facilities and information 
The Corporation and the Department shall cooperate fully with the Nuclear Regulatory Commission and the Environmental Protection Agency and shall provide the Nuclear Regulatory Commission and the Environmental Protection Agency with the ready access to the facilities, personnel, and information the Nuclear Regulatory Commission and the Environmental Protection Agency consider necessary to carry out their responsibilities under this subsection. A contractor operating a Corporation facility for the Corporation shall provide the Nuclear Regulatory Commission and the Environmental Protection Agency with ready access to the facilities, personnel, and information of the contractor as the Nuclear Regulatory Commission and the Environmental Protection Agency consider necessary to carry out their responsibilities under this subsection.
(C) Limitation 
The Nuclear Regulatory Commission shall limit its finding under subsection (b)(2) of this section to a determination of whether the facilities are in compliance with the standards established under subsection (a) of this section.
(d) Requirement for operation 
The gaseous diffusion uranium enrichment facilities of the Department may not be operated by the Corporation unless the Nuclear Regulatory Commission, in consultation with the Environmental Protection Agency, makes a determination of compliance under subsection (b) of this section or approves a plan prepared by the Department for achieving compliance required under subsection (b) of this section.

42 USC 2297f1 - Licensing of other technologies

(a) In general 
Corporation facilities using alternative technologies for uranium enrichment, including AVLIS, shall be licensed under sections 2073, 2093, and 2243 of this title.
(b) Costs for decontamination and decommissioning 
The Corporation shall provide for the costs of decontamination and decommissioning of any Corporation facilities described in subsection (a) of this section in accordance with the requirements of the amendments made by section 5 of the Solar, Wind, Waste, and Geothermal Power Production Act of 1990.

42 USC 2297f2 - Regulation of Restricted Data

The Corporation shall be subject to this chapter with respect to the use of, or access to, Restricted Data to the same extent as any private corporation.