current Baseline Estimate
Defined in 4 places of the United States Code.
(A) The term "current Baseline Estimate" means the projected total acquisition cost of a major system that is—
(i) approved by the Director, or a designee of the Director, at Milestone B or an equivalent acquisition decision for the development, procurement, and construction of such system;
(ii) approved by the Director at the time such system is restructured pursuant to section 3102(c) of this title; or
(iii) the 2010 adjusted total acquisition cost determined pursuant to subsection (h).
(B) A current Baseline Estimate may be in the form of an independent cost estimate.
Source
- 2013–202650 U.S.C. § 3101War and National Defense · Reports on the acquisition of major systems · in this section
(A) The term “current Baseline Estimate” means the projected total acquisition cost of a major system that is—
(i) approved by the Director, or a designee of the Director, at Milestone B or an equivalent acquisition decision for the development, procurement, and construction of such system;
(ii) approved by the Director at the time such system is restructured pursuant to section 415a–8(c) of this title; or
(iii) the 2010 adjusted total acquisition cost determined pursuant to subsection (h).
(B) A current Baseline Estimate may be in the form of an independent cost estimate.
Source
- 2010–present50 U.S.C. § 415a-7War and National Defense · Transferred · in this section
In this section, the terms “cost estimate”, “critical cost growth threshold”, “current Baseline Estimate”, “major system”, and “total acquisition cost” have the meaning given those terms in section 3101(a) of this title.
Source
- 2013–present50 U.S.C. § 3102War and National Defense · Critical cost growth in major systems · in this section
In this section, the terms “cost estimate”, “critical cost growth threshold”, “current Baseline Estimate”, “major system”, and “total acquisition cost” have the meaning given those terms in section 415a–7(a) of this title.
Source
- 2010–present50 U.S.C. § 415a-8War and National Defense · Transferred · in this section
The term “current Baseline Estimate” means the projected total acquisition cost of a major system that is—
(i) approved by the Director, or a designee of the Director, at Milestone B or an equivalent acquisition decision for the development, procurement, and construction of such system;
(ii) approved by the Director at the time such system is restructured pursuant to section 3102(c) of this title; or
(iii) the 2010 adjusted total acquisition cost determined pursuant to subsection (h).
Source
- 2026–present50 U.S.C. § 3101War and National Defense · Reports on the acquisition of major systems · in this section