Request for proposals

Acts 2017, No. 809, § 1.

(1) A request for proposals under this subchapter shall include without limitation the following: The minimum qualifications of the construction manager-general contractor;

(2) The procedures for submitting a proposal to the Arkansas Department of Transportation, the criteria for the evaluation of and selection of a construction manager-general contractor to perform preconstruction services, and the relative weight assigned for each criteria as indicated in a technical scoring matrix;

(3) The form of the contract to be awarded for preconstruction services;

(4) A listing of the types and scope of the preconstruction services that will be required;

(5) The scope of the intended contract;

(6) The budget limits for the transportation project and the preconstruction services;

(7) The method of payment and structure of fees for the preconstruction services;

(8) A requirement that the construction manager-general contractor submit relevant information regarding any licenses, registration, or credentials that may be required to construct the transportation project;

(9) A requirement that the construction manager-general contractor provide evidence that establishes that the construction manager-general contractor is capable of obtaining the required bonding and insurance;

(10) A requirement that the construction manager-general contractor submit information concerning the debarment or default from a federal, state, or local government transportation project within the past five (5) years;

(11) A requirement that the construction manager-general contractor provide information concerning the bankruptcy or receivership of any of its members, including information concerning any work completed by a surety;

(12) A requirement that the construction manager-general contractor provide evidence of competency, capability, and capacity to complete a transportation project of similar size, scope, or complexity; and

(13) A prohibition that excludes a person or firm that has received compensation for assisting the department in preparing the request for proposals from submitting a proposal in response to the request for proposals or participating as a construction manager-general contractor team member.

(14) A request for proposals under this subchapter shall not: Require that the construction manager-general contractor have prior experience with any particular transportation project procurement method as a condition for submitting a proposal; and

(15) Give any preference for any particular contract delivery method in the scoring of a proposal.

(16) The department shall: Send a written notice of award to the best-evaluated construction manager-general contractor; or

(17) Send to all the construction manager-general contractors that submitted a proposal a written notice that all proposals have been rejected.

Current official text: Arkansas General Assembly. Digitized from the UniCourt Code Improvement Commission public-domain capture. Reproduced from public-domain Arkansas statutes; confirm against the official source for the current text. Not legal advice.