Public-domain · open source
OpenJurist

A.R.S. § 49-1211

Project delivery methods

The authority may provide for the development or operation of water-related facilities using a variety of project delivery methods and forms of agreement. The methods may include:

1. Predevelopment agreements leading to other implementing agreements.

2. A design-build agreement.

3. A design-build-maintain agreement.

4. A design-build-finance-operate agreement.

5. A design-build-operate-maintain agreement.

6. A design-build-finance-operate-maintain agreement.

7. A concession agreement providing for the private partner to design, build, operate, maintain, manage or lease a water-related facility.

8. Any other project delivery method or agreement or combination of methods or agreements that the authority determines are reasonable or necessary to carry out the authority's purposes.

Official source: Arizona State Legislature. Reproduced from public-domain Arizona statutes; confirm against the official source for the current text. Not legal advice.