Cal. Civ. Code § 8180

Completion

Applied in 1 court decision — leading case Cavu/Rock Properties Project I, LLC v. Gold Star Construction, Inc. (In re Cavu/Rock Properties Project I, LLC) (2014)

Most recently applied in Cavu/Rock Properties Project I, LLC v. Gold Star Construction, Inc. (In re Cavu/Rock Properties Project I, LLC) (August 2014)

Added by Stats. 2010, Ch. 697, Sec. 20

(a) For the purpose of this title, completion of a work of improvement occurs upon the occurrence of any of the following events:

(1) Actual completion of the work of improvement.

(2) Occupation or use by the owner accompanied by cessation of labor.

(3) Cessation of labor for a continuous period of 60 days.

(4) Recordation of a notice of cessation after cessation of labor for a continuous period of 30 days.

(b) Notwithstanding subdivision (a), if a work of improvement is subject to acceptance by a public entity, completion occurs on acceptance.

Official source: California Legislative Information. Reproduced from public-domain California statutes; confirm against the official source for the current text. Not legal advice.