Public-domain · open source
OpenJurist

Cal. Civ. Code § 8186

Completion

Added by Stats. 2010, Ch. 697, Sec. 20

If a work of improvement is made pursuant to two or more direct contracts, each covering a portion of the work of improvement:

(a) The owner may record a notice of completion of a direct contract for a portion of the work of improvement. On recordation of the notice of completion, for the purpose of Sections 8412 and 8414, a direct contractor is deemed to have completed the contract for which the notice of completion is recorded and a claimant other than a direct contractor is deemed to have ceased providing work.

(b) If the owner does not record a notice of completion under this section, the period for recording a claim of lien is that provided in Sections 8412 and 8414.

Official source: California Legislative Information. Reproduced from public-domain California statutes; confirm against the official source for the current text. Not legal advice.