In the event that a development project requires more than one approval by a public agency, such agency may establish time limits (1) for submitting the information required in connection with each separate request for approval and (2) for acting upon each such request; provided, however, that the time period for acting on all such requests shall not, in aggregate, exceed those limits specified in Sections 65950 and 65952.
Cal. Gov. Code § 65957.1
Approval of Development Permits
Known as the Permit Streamlining Act
The act spans §§ 65920–65964 (70 sections).
Added by Stats. 1978, Ch. 1113.
Official source: California Legislative Information. Reproduced from public-domain California statutes; confirm against the official source for the current text. Not legal advice.