Construction Manager/General Contractor Procurement Method for the Department of Water Resources

Known as the State Contract Act

The act spans §§ 10100–10285 (181 sections).

Added by Stats. 2021, Ch. 247, Sec. 1

(a) The department shall prepare and submit to the Legislature an interim report no later than July 1, 2025, that describes each Construction Manager/General Contractor project approved under this article beginning January 1, 2022, and that provides relevant data, including, but not limited to, cost, the stage of completion, and estimated time to completion.

(b) The department shall prepare and submit to the Legislature a final report, no later than July 1, 2028, that provides the relevant data referenced in subdivision (a) for projects that were approved under this article as of January 1, 2027.

(c) Both the interim and final reports shall provide a comprehensive assessment on the effectiveness of the Construction Manager/General Contractor project delivery method relative to project cost and time savings.

(d) A report to be submitted pursuant to this subdivision shall be submitted in compliance with Section 9795 of the Government Code.