Cal. Pub. Res. Code § 25530

Power Facility and Site Certification

Known as the Warren-Alquist State Energy Resources Conservation and Development Act

The act spans §§ 25000–25997 (502 sections).

Applied in 1 court decision — leading case 105 Cal. App. 4th 1441 - Santa Teresa Citizen Action Group v. State Energy Resources Conservation & Development Commission (2003)

Most recently applied in 105 Cal. App. 4th 1441 - Santa Teresa Citizen Action Group v. State Energy Resources Conservation & Development Commission (February 2003)

Added by Stats. 1974, Ch. 276.

The commission may order a reconsideration of all or part of a decision or order on its own motion or on petition of any party.

Any such petition shall be filed within 30 days after adoption by the commission of a decision or order. The commission shall not order a reconsideration on its own motion more than 30 days after it has adopted a decison or order. The commission shall order or deny reconsideration on a petition therefor within 30 days after the petition is filed.

A decision or order may be reconsidered by the commission on the basis of all pertinent portions of the record together with such argument as the commission may permit, or the commission may hold a further hearing, after notice to all interested persons. A decision or order of the commission on reconsideration shall have the same force and effect as an original order or decision.