Conn. Gen. Stat. § 13b-31f

Ninety-day permit application final determinations

Known as the State Transportation Act

The act spans §§ 13b-1 to 13b-57a (159 sections).

(June Sp

Notwithstanding any provision of the general statutes, the Department of Transportation shall review and make a final determination on each of the following types of permit applications not later than ninety days after receipt of such application: (1) Encroachment, (2) parkway, (3) industrial truck, (4) outdoor advertising, and (5) specific information signs on limited access highways. Following such ninety-day period, if a final determination on such an application is not made by said agency, such application shall be deemed approved.