Conn. Gen. Stat. § 16-50jj

Meeting conducted during construction of electric generating facility

Known as the Public Utility Environmental Standards Act

The act spans §§ 16–16 (33 sections).

(P.A. 11-51, S. 134; 11-101, S. 3; P.A. 13-247, S. 222.) History: P.A. 11-101 effective July 8, 2011; pursuant to P.A. 11-51, “Department of Emergency Management and Homeland Se…

At least once during the period of construction of an electric generating facility in this state, the Connecticut Siting Council, the Departments of Administrative Services, Emergency Services and Public Protection and Consumer Protection and the Labor Department shall conduct a meeting to discuss and develop proposed resolutions for any known or potential safety issue at such facility. The council and said departments shall submit any such proposed resolutions to the special inspector provided for such facility, as required pursuant to section 16-50ii .

Official source: Connecticut General Assembly. Reproduced from public-domain Connecticut statutes; confirm against the official source for the current text. Not legal advice.